New for disasters declared on or after September 1, 2026
FEMA now lets experienced applicants work through Public Assistance without an assigned Program Delivery Manager. If you take that path, your project documents and cost estimates have to make the whole case on their own. This page explains how the new process works and how to build estimates that hold up.
What changed
Until now, FEMA delivered Public Assistance by assigning a Program Delivery Manager (PDMG) to each applicant: your main point of contact, who guided you through every step. For all incidents declared on or after September 1, 2026, FEMA lets applicants navigate the process without a PDMG. FEMA calls this “Applicant-Managed.”
FEMA says the goal is to build applicant and recipient capability. In practice, it moves work that a PDMG used to carry, such as organizing damage, shaping projects and assembling documentation, onto applicants who say they can handle it.
The RPA choice
In Section II of the RPA, “Applicant Experience,” you describe your experience with the Public Assistance process. If you select “Familiar, and likely to be comfortable with limited or remote support navigating the process,” FEMA does not assign a PDMG. Your state or other recipient then decides whether to assign one of its own.
Other experience answers
FEMA PDMG
FEMA assigns a Program Delivery Manager who guides you through recovery scoping, project development and deadlines, as before.
“Familiar…” + recipient says yes
Recipient-Led
Your state assigns a PDMG from its own staff (shown in Grants Portal as a state PDMG). You still get a guide, just not from FEMA.
“Familiar…” + recipient says no
Applicant-Managed
No PDMG. FEMA assigns a Program Delivery Task Force Leader (PDTFL), who reviews your projects rather than building them with you.
Decide on purpose. The RPA is due within 30 days of your area’s designation, often while you are still in response mode. Choose “Familiar” only if you are ready to run your own projects. FEMA can add a PDMG later if you ask or fall behind, but once you have a PDMG, FEMA will not switch you to Applicant-Managed.
Your process
Estimating is your job now
For estimated-cost projects, Grants Manager normally prompts FEMA to review the “Development Guide Answers” a PDMG fills in. Applicants can’t complete the Development Guide, so under Applicant-Managed the PDTFL skips it and checks your documents instead. FEMA’s guide is specific about what those documents should include: a detailed scope of work, any hazard mitigation proposals, and itemized estimated or actual costs.
Nobody on FEMA’s side is building the estimate with you, so it needs to be clear, sourced and checkable on first read.
FEMA’s cost estimating course uses a simple case: replacing one commercial exterior fire-rated steel door, frame and hardware.
None of these is “wrong.” They price different scopes. The course’s lesson is that most gaps between FEMA, owner and contractor estimates come from three different scopes of work: the eligible scope, the scope the owner wants (which may include improvements), and the scope in the bid documents. Align the scopes first, and the numbers usually follow.
Built from: Quick Guide, “Project Reviews,” p. 7; FEMA course “Costing Estimates and Cost Estimating Format,” Lessons 1–2 (door scenario; “Difference in Cost Estimates”; “Alignment of Estimates”).Choosing a method
An estimate grows up as you learn more. Florida’s Division of Emergency Management teaches four stages, each building on the last:
| Stage | What the estimate is for | Methods that fit |
|---|---|---|
| Initial Damage Assessment (IDA) | Show the impact is big enough to request a joint assessment and a declaration | Analogous (past similar projects), square-foot, local historical costs |
| Joint Preliminary Damage Assessment | Refine and validate impacts with state and FEMA partners | Square-foot and parametric, checked against insurance policies, schedules of values, photos, GPS locations, maintenance records |
| Damage inventory line items | Report each damaged element in Grants Portal | Measured quantities with unit costs |
| Project formulation | The number your project is funded on | Detailed unit-cost estimate; the Cost Estimating Format for large permanent work |
Analogous estimating
Best for: first numbers, IDAs
Uses costs from past, similar projects. Quick and top-down, useful when you know little. Not detailed enough to fund a project on.
Square-foot models
Best for: whole-building screening
Prices a building by its area and type. Published models such as RSMeans square-foot costs from Gordian let you adjust for building type, construction, height and location. Useful for replacement values, early budgets, checking insurance schedules of values, and a first look at the 50 percent rule. Too coarse to fund a repair scope.
Parametric estimating
Best for: fast, consistent early funding
Uses statistical relationships between cost drivers (area, lane-miles, capacity, facility type) and cost. FEMA’s own RAPID process (Rapid Assessment with Public Infrastructure Data) uses public data to speed grant formulation for significantly damaged infrastructure. Treat parametric numbers as a starting point to be checked against real scope and prices.
Detailed unit-cost estimating
Best for: the funded project
Every element of work quantified and priced: labor, materials, equipment and markups. This is what FEMA’s review is built around. Unit costs, not lump sums.
Cost data
FEMA’s cost estimating training ranks cost data sources. Use the highest one you can support, and say in the estimate which source each line uses.
Local historical costs. Recent, competitively procured contracts for similar work, by you or nearby agencies, with a schedule of values or unit rates. State DOT bid prices are a common source. FEMA’s training calls these the most reliable data.
Published industry cost data. Current editions of industry-standard data. Appendix L of the PAPPG names RSMeans, Xactimate, BNi, Marshall & Swift and Sweet’s. Apply the publication’s locality factor to each line, and remember that book unit costs usually cover the installing contractor only, so general contractor costs come in through the CEF factors.
FEMA cost codes. Issued by the FEMA region for a location or declaration, usually as complete installed costs. Some are several years old and need escalation.
For applicant-owned equipment, FEMA’s Schedule of Equipment Rates applies; see force account equipment rates. If you buy repair work through a competitively procured job order contract, its priced task orders are strong cost support.
Disaster markets don’t match the books. After a large event, contractors get scarce, materials get rationed, and remote or island locations pay heavy mobilization costs. Document these conditions with quotes, bids and supplier letters rather than quietly inflating unit prices.
The Cost Estimating Format
The Cost Estimating Format (CEF) is FEMA’s standard method for estimating large permanent work. When FEMA writes the estimate for a large project in Categories C to G that is less than 90 percent complete, it uses the CEF. For other projects, FEMA’s training recommends organizing your estimate the same way, even when the CEF isn’t required.
Bar widths are illustrative only, not FEMA percentages. Navy parts build the construction cost; crimson parts are the owner’s non-construction costs. Select a part.
Contingencies are the most misunderstood part (Part C). They pay for genuine uncertainty in executing a defined scope, not for scope you haven’t identified. Escalation (Part E) prices the work forward to the midpoint of construction. The CEF Instructional Guide sets the factor ranges, and only FEMA Headquarters can approve factors outside them.
Built from: FEMA course “Costing Estimates and Cost Estimating Format,” Lesson 3: CEF requirements and Parts A–H; GovStar topic Applicant and FEMA cost estimates (PAPPG Chapter 9, pp. 232–233: CEF use, factor ranges, capped projects); GovStar Chapter Overview Cost Estimating Format (CEF).How FEMA checks your estimate
FEMA staff must use the Appendix L checklist on applicant estimates for large permanent work, and may use parts of it for emergency work. Under Applicant-Managed, the PDTFL is applying these checks to documents you wrote alone. Build to them from the start.
For replacement requests, FEMA’s training notes a licensed FEMA engineer, architect or certified estimator reviews the estimates, with an added U.S. Army Corps of Engineers review above $5 million.
Built from: GovStar topics Cost estimate validation checklist, sources and unit costs, reasonableness test (PAPPG Appendix L, pp. 319–321) and applicant and FEMA cost estimates; F-ROC training (Appendix L applicability; Simplified Procedures Appendix A sets expectations for estimate support); FEMA course, “Third-Party Expert Panel Review.” Reviewer: please confirm the $5 million replacement review is still current before publishing.Readiness check
Answer honestly for your organization as it is today. Your answers stay in your browser.
Built from: Quick Guide applicant responsibilities; PAPPG requirements via GovStar topics (impact list, scope of work, Appendix L, procurement, insurance); GovStar Cost Estimating Challenges and RAPID Approval Readiness (pre-disaster readiness actions: asset profiles, local unit-cost libraries, pre-procured estimating support); F-ROC JPDA checklist. Reviewer: scoring bands (16+ ready, 10–15 ready with support, under 10 ask for a PDMG) are a GovStar judgment call for you to set.Watch out
Get help
GovStar works with local governments, tribes and nonprofits on scopes, cost estimates and FEMA-ready project documentation, remotely.