The Applicant incurred an additional $33,046.28 associated with the project’s approved scope of work. This additional cost is eligible for reimbursement because it is associated with previously approved work and within the project’s approved timeframe. The remainder of the Applicant’s claimed costs are associated with work performed after the project’s approved timeframe. The Applicant did not report the additional work until after the December 31, 2022 work reporting deadline and did not demonstrate that there were extenuating circumstances beyond its control to justify extending the deadline. Therefore, this appeal is partially granted.