Change in Scope of Work

Scope of Work

HEADNOTES

An applicant is responsible for identifying all disaster related work, requesting inspections and changes in PWs, and obtaining FEMA’s prior approval for any SOW revision. The Applicant did not request a SOW change from FEMA prior to commencing and completing work.

CONCLUSION

The work completed by the Applicant was performed outside the approved SOW and without the prior approval required for a SOW change. Therefore, this appeal is denied.

AUTHORITIES

Stafford Act §406(a)(1). 2 C.F.R. § 200.308(c)(1). 44 C.F.R. §§ 206.203(d)(1), 206.204(e), 206.205(b)(1)(2). PAPPG, at 139.

44 C.F.R. §§ 206.203(d)(1), 206.204(e), 206.205(b)(1)(2)