Time Limitations/Extensions

Time Extensions

HEADNOTES

44 C.F.R. § 206.204(d)(2) provides that if FEMA denies a time extension request, the applicant may still be reimbursed for eligible project costs, but only those incurred up to the latest approved completion date. The Applicant completed the original approved $29,366.84 in repair work after the latest approved project completion date, and so those costs are not eligible for reimbursement. Stafford Act § 301 provides that FEMA may also, if so requested by an applicant, modify or waive, for a major disaster, such administrative conditions for assistance as would otherwise prevent the giving of assistance under such programs if the inability to meet such conditions is a result of the major disaster. The Applicant has not demonstrated the failure to complete the permanent repair work within the POP was a result of this disaster.

CONCLUSION

AUTHORITIES

Stafford Act §§ 301, 406(a)(1)(A), 705(c). 44 C.F.R. §§ 13.30(d)(1), 13.43(a)(2), 206.204(c)-(d). PA Guide, at 110, 138-140. Nashville-Davidson Cnty., FEMA-1909-DR-TN, at 4.

44 C.F.R. §§ 13.30(d)(1), 13.43(a)(2), 206.204(c)-(d)
Time Limitations/Extensions