Per 44 C.F.R. 13.30(d); an applicant must obtain FEMA approval prior to revising the scope of work (SOW).The Applicant repaved the Facility access road without FEMA approval.Work to repave the road is ineligible.

Codes and Standards, Change in Scope of Work, Financial Accounting and Reconciliation
2017

PA Guide; at 27-28; 115.Lawrence County Engineer; FEMA-4002-DR-OH; at 6.Department of Transportation; FEMA-4068-DR-FL; at 5.HeadnotesPer 44 C.F.R. § 13.30(d); an applicant must obtain FEMA’s approval prior to revising the scope of work (SOW).The Applicant repaved the Facility access road without FEMA approval.Work to repave the road is ineligible.