Cost Estimating Format for Large Projects

Summary & Key Issues

Return to >>
Cost-Estimating

Body 1 Discussion

Cost Estimating Format for Large Projects

‍The Cost Estimating Format Tool

CEF is comprised of eight parts that reflect the proposed costs associated with each large project. The structure of the tool mirrors the applicant-general contractor-subcontractor relationship for eligible work.

  • Part A - Base construction cost for labor, equipment and materials required to perform eligible work.
  • Part B – Costs associated with work execution such as temporary services and utilities, safety and security measures, field supervision, quality control and administrative submittals.
  • Part C – Construction cost contingencies such as project unknowns and complexities, and the degree of difficulty for site access, storage, and staging.
  • Part D – Applies to contracted work for the general (or prime) contractor's home office overhead, insurance, bonds, and profit.
  • Part E – Accounts for cost escalation at certain points over the duration of the project.
  • Part F – Fees for building permits, plan checks and special reviews.
  • Part G – Owner's reserve for change orders and differing site conditions.
  • Part H – The applicant's project management and design costs.

‍

‍

Body 2 Discussion

Cost Estimating Format for Large Projects

Body 3 Discussion

Cost Estimating Format for Large Projects

Body 4 Discussion

Cost Estimating Format for Large Projects