Appendix I › IV. Work Eligibility Considerations for Buildings, Equipment, and Vehicles
What building, equipment and vehicle work is eligible, and what isn’t?
Short answer
Eligible: mud and water removal, mold remediation, bracing and sandbagging, demolition for an immediate threat, safety placarding inspections, earthquake frame evaluations, and repair or replacement of buildings, equipment and vehicles to pre-disaster condition. Not eligible: mold from poor maintenance, unneeded slab removal, code and substantial-damage inspections, extra capacity for growth, and ADA fixes you were already cited for.
What FEMA requires
- Common EHP laws: NEPA, NHPA, Clean Air Act, ESA, EOs 11988 and 11990.
- Mud and silt removal needed to restore the facility is permanent work (Category E) and must be done with the restoration.
- Demolition may not be eligible if securing the structure and area is enough to protect the public.
- Earthquake frame repair to pre-earthquake design under FEMA 352 Chapter 6 is eligible only if FEMA approves a specific scope before the work; related architectural finishes and fire retardants are also eligible.
- Restoration: provide construction dates; check historic register listings; identify floodplain location (1% chance, or 0.2% for critical actions); consider building, roof and system age and maintenance to separate disaster damage from pre-existing damage; comply with required codes.
- Public housing authority facilities are eligible for permanent work only if Congress does not appropriate HUD funds for emergency capital needs for the facility.
<table class="pt-table"><thead><tr><th>Work</th><th>Eligible</th><th>Not eligible</th></tr></thead><tbody><tr><td>Water, mud and silt removal (B)</td><td>From eligible facilities, done quickly to address an immediate threat</td><td>On private property unless the threat is widespread, you have legal authority, and you have rights-of-entry and hold-harmless agreements</td></tr><tr><td>Mold remediation (B or E)</td><td>For an immediate threat or with restoration, including post-remediation sampling</td><td>Mold from poor maintenance or failure to protect the facility promptly; pre-remediation sampling that finds no mold</td></tr><tr><td>Emergency protective measures (B)</td><td>Bracing, shoring, barricades, fencing, sandbagging, emergency repairs</td><td>None listed</td></tr><tr><td>Demolition (B)</td><td>For an immediate threat, including imminently collapsing private structures</td><td>Removing slabs, foundations, pads or driveways that pose no hazard (except HMGP buyouts)</td></tr><tr><td>Safety inspections (B and I)</td><td>Placarding public and private buildings for safe entry and use</td><td>Inspections for elevation or relocation decisions, code compliance, substantial damage, or flood-fight fill removal</td></tr><tr><td>Earthquake steel frame evaluation (E)</td><td>Evaluating welded steel moment frames for disaster damage; approved repairs</td><td>Preliminary screening, analytical studies, and inspections that find no significant damage</td></tr><tr><td>Restoration (E)</td><td>Repair or replacement to pre-disaster design, capacity and function; like-for-like equipment and vehicles</td><td>Tax assessments; added capacity for growth; ADA fixes you were cited for before the incident</td></tr></tbody></table>
Documentation
Construction dates of all buildings in the project; National or state historic register status; floodplain status; age and maintenance records for the roof and building systems; mold sampling results; and, for earthquake frame repairs, FEMA’s approved scope before work begins.
Watch out · Govstar advice
Mold is lost most often to delay. If you can’t dry a building quickly, document why (no power, no access) and the steps you took, so the mold isn’t blamed on a failure to protect the facility.