Can we hire a contractor without competitive bidding in an emergency?

FEMA term
Noncompetitive procurement; exigency or emergency
Short answer

Yes, but only under one of four circumstances, only for work tied to that circumstance, and only while it lasts. Start a competitive procurement right away and move to a competed contract as soon as the emergency or exigency ends.

What FEMA requires

A sole-source contract is allowed only when:

  • The item is available from only one source;
  • A public exigency or emergency won’t permit the delay of competition;
  • FEMA or the recipient authorizes it in writing at your request; or
  • Competition proved inadequate after soliciting several sources.

For large projects, document which circumstance applied, a description and expected amount, why competition wasn’t possible, how long the contract will be used, the steps you took to try to compete, and any conflicts of interest. Failing to plan the transition is not a reason to keep using a sole-source contract.

Documentation

A written justification covering each of the points above, prepared when the decision was made.

Watch out · Govstar practitioner advice

Emergency (immediate threats, such as clearing roads for rescue) and exigency (urgent but not life-threatening, such as reopening a school by September) are different. Name the one that applies and set an end date.

GovStar deeper dive

Going further: how it works in practice

Practitioner explainers for this topic, with the takeaways that matter most.

Procurement under exigent or emergency circumstances

The federal procurement rules at 2 C.F.R. §§ 200.317–200.327 govern non-competitive, "sole-source" contracting under exigent or emergency circumstances. FEMA defines an emergency as an active threat to life or safety requiring immediate action, while an exigency involves a need to prevent serious programmatic or financial harm where competitive delays would be unacceptable.

Non-competitive contracts are only valid for the duration of the actual emergency. Non-state entities must immediately begin a competitive bidding process while the emergency work is active, transitioning away from the sole-source contract as soon as conditions stabilize.

Key takeaways

  1. Incorporate Appendix II Clauses in Sole-Source Files: Verify that emergency sole-source agreements contain every mandatory federal clause and anti-kickback provision listed in 2 CFR Part 200 Appendix II.
  2. Transition to Open Bidding Immediately: Initiate a standard, competitive procurement solicitation for identical services concurrently while an emergency contract is active.
  3. Execute a Cost Analysis for Emergency Awards: Conduct and document a formal independent cost or price analysis for any emergency contract expected to exceed the federal simplified acquisition threshold.
  4. Draft a Separate Justification per Procurement: Compile a standalone written justification for every non-competitive contract, explicitly identifying which of the four permitted circumstances in 2 CFR § 200.320(c) caused the exception.
  5. Observe Strict State versus Non-State Definitions: Adhere to state-level procurement laws if operating as a state instrumentality, while local municipalities and PNPs must follow the stricter non-state entity sole-source rules.

Full guide: see the “Sole Source & Emergencies” section of GovStar’s Procurement and Contracting Guide, including what a justification should contain.