A cost is reasonable if a prudent person would have paid it under the circumstances at the time. FEMA analyzes reasonableness for contract work bought without competition, time-and-materials or cost-plus-percentage contracts, and noncompliant procurements on large projects. For your own staff and equipment, it reviews only large projects.
FEMA weighs whether:
FEMA also considers shortages, project complexity, economy of scale, extraordinary labor needs and your written justification. If a cost is not reasonable, FEMA may fund only the reasonable portion, using the least-cost alternative, the lowest bid, another applicant’s properly procured price or a FEMA estimate.
Bid tabulations, your cost or price analysis, historical invoices for similar work, and a written justification for any cost above market, prepared at the time.
Write down why prices were high while it is happening: shortages, haul distances, access problems. A justification reconstructed months later carries far less weight.
Per 2 CFR 200.404, a cost is considered eligible only if it is reasonable and necessary. A cost is deemed reasonable if, in its nature and amount, it does not exceed what a prudent person would incur under the circumstances prevailing at the time the decision was made. Reasonable costs must be fair, equitable, directly tied to eligible work, adequately documented, and compliant with all federal, state, and local procurement laws. Reasonable pricing thresholds are established via historical documentation, local market averages, national cost-estimating databases, and FEMA's own equipment rates and design service curves.
FEMA evaluates cost reasonableness by checking for ordinary/necessary facility standards, market price consistency, compliance with open procurement requirements, and ethical business practices (ensuring independent, arm's-length transactions free of familial or shared-interest conflicts).
FEMA also reviews potential cost escalation factors, such as regional resource shortages or project complexities (e.g., environmental or historic preservation issues, remote access, or unique service needs). In exigent circumstances, the duration of the emergency is compared against the duration of the elevated expenses. The applicant bears full responsibility for proving cost reasonableness. If FEMA deems a cost unreasonable, it may adjust or disallow the funding in part or in whole. For incomplete work, estimates must be unit-based (not lump sum) and certified by a licensed Professional Engineer or estimator to match the agreed scope of work.