FEMA reimburses fixed-price and cost-reimbursement contracts, and time-and-materials contracts only in limited cases. Cost-plus-percentage-of-cost and percentage-of-construction pricing is prohibited.
You must oversee every contract to make sure the contractor performs to its terms. Time-and-materials (and time-and-equipment) contracts are used only for a reasonable period until you can define the scope of work.
For time-and-materials contracts, daily or weekly logs or records of performance meetings showing oversight. Source: PAPPG Table 15.
Convert time-and-materials work to a fixed-price or unit-price contract as soon as the scope is clear. The longer it runs, the harder it is to defend.
FEMA’s Procurement Under Grants Policy Guide treats contract type as a cost-control decision. Fixed-price contracts put the cost risk on the contractor and suit well-defined work. Cost-reimbursement contracts need a ceiling and close monitoring.
A time-and-materials contract gives the contractor no incentive to control labor hours, so local governments and nonprofits may use one only after determining that no other contract type is suitable and that the contract has a ceiling price the contractor exceeds at its own risk. Materials are billed at cost; profit is allowed only inside the fixed hourly labor rates.
A contract is a prohibited cost-plus-a-percentage-of-cost contract when payment is a predetermined percentage, applied to actual costs, the contractor’s entitlement is uncertain at signing, and it grows as costs grow. Watch for “T&M” contracts that add a percentage markup to materials or subcontracts.
Full guide: see “Who Follows What” and “Cost & Bonding” in GovStar’s Procurement and Contracting Guide.