You must follow your own written procurement procedures, your state and local laws, and the federal rules in 2 CFR 200.318–200.327, using whichever is most restrictive. If you don’t comply, FEMA can deny all contract costs or pay only the portion it finds reasonable.
Your procurement policy, solicitations, bids, selection documentation, cost or price analysis, contracts, change orders and invoices. Source: PAPPG Table 15.
A prequalified contractor list is not a contract. You still have to compete the work, and you can’t exclude firms that weren’t on the list.
The federal procurement standards at 2 C.F.R. §§ 200.317–200.327 apply to every Public Assistance contract. Which version applies depends on your disaster declaration date: the revised rules and FEMA’s Procurement Under Grants Policy Guide cover disasters declared on or after October 1, 2024, and the dollar thresholds follow the purchase date ($15,000 and $350,000 from October 1, 2025).
The procurement methods FEMA recognizes are:
Time-and-materials contracts are allowed only when no other contract type is suitable, with a ceiling price the contractor exceeds at its own risk and a high degree of oversight. Cost-plus-a-percentage-of-cost contracts are prohibited.
Full guide: for the complete rules with page citations, a method selector and a contract clause checklist, see GovStar’s Procurement and Contracting Guide.