How does FEMA decide whether our estimate’s costs are reasonable?
- FEMA checks a representative sample for reasonable costs. Unreasonable items send the estimate back for revision.
- All items must be eligible; FEMA removes ineligible items and documents why.
- All work activities must be quantified with unit costs. Lump sums that need to be converted to unit prices send the estimate back.
- The correct locality adjustment factor from the cost publication must be applied to each line item. Where historical costs were used, no locality adjustment is applied, but escalation factors are added.
- Cost items are checked against local weighted average unit prices or industry cost data: at least six of the ten largest items (or all items if fewer than ten), individually, and at least 25 percent of the rest must be within 10 percent. If not, the estimate is returned for revision.
- The reviewer records the review date, any information requests, and signs the checklist.
Backup for your largest cost items, local weighted average unit prices or cost data references, the locality adjustment factors used, and escalation factors where you used historical costs.