Yes, with FEMA approval, if restoring the original function doesn’t serve the public welfare. Funds go to a permanent work project benefiting the public in the same general area, capped at the lesser of the federal share of the restoration estimate or of actual costs.
Your request explaining why restoration doesn’t serve the public, the alternate project scope and location, and FEMA approval.
Requesting an alternate project ends temporary facility funding for that service. Time the request accordingly.
When restoring a damaged facility’s original function no longer serves the public welfare, applicants may ask FEMA to redirect the funds to an Alternate Project: another permanent work project benefiting the public in the same general area. Allowed uses include repairing, expanding or building other eligible facilities, demolition, capital equipment of $10,000 or more per unit, cost-effective mitigation, and supplementing an improved project.
FEMA must approve the alternate project before construction starts, so it can review environmental compliance. Funding is capped at the lesser of the federal share of the restoration estimate or the federal share of actual costs. Alternate project funds cannot cover operating expenses, budget shortfalls, items under $10,000, the non-federal share of any PA project, or projects in a regulatory floodway.