Can we use the funds for a different facility instead of rebuilding the damaged one?

FEMA term
Alternate project (capped)
Short answer

Yes, with FEMA approval, if restoring the original function doesn’t serve the public welfare. Funds go to a permanent work project benefiting the public in the same general area, capped at the lesser of the federal share of the restoration estimate or of actual costs.

What FEMA requires

  • Allowed uses: repairing, expanding, mitigating or building other eligible facilities; demolition; capital equipment of $10,000 or more per unit; covering flood insurance reductions in flood hazard areas; supplementing an improved project; and cost-effective mitigation.
  • Not allowed: budget shortfalls, community plans, landscaping, operating expenses, items under $10,000, the non-federal share of any PA project, buyouts, projects using other federal grants, or projects in a floodway.
  • Construction needs FEMA approval before it starts, for environmental compliance.
  • Mitigation included in the original scope is dropped from the alternate project cap.
  • Temporary facility costs stop when you request an alternate project.

Documentation

Your request explaining why restoration doesn’t serve the public, the alternate project scope and location, and FEMA approval.

Watch out · Govstar practitioner advice

Requesting an alternate project ends temporary facility funding for that service. Time the request accordingly.

GovStar deeper dive

Going further: how it works in practice

Practitioner explainers for this topic, with the takeaways that matter most.

Alternate projects

When restoring a damaged facility’s original function no longer serves the public welfare, applicants may ask FEMA to redirect the funds to an Alternate Project: another permanent work project benefiting the public in the same general area. Allowed uses include repairing, expanding or building other eligible facilities, demolition, capital equipment of $10,000 or more per unit, cost-effective mitigation, and supplementing an improved project.

FEMA must approve the alternate project before construction starts, so it can review environmental compliance. Funding is capped at the lesser of the federal share of the restoration estimate or the federal share of actual costs. Alternate project funds cannot cover operating expenses, budget shortfalls, items under $10,000, the non-federal share of any PA project, or projects in a regulatory floodway.

Key takeaways

  1. Get FEMA Approval Before Construction: Submit the alternate project request early and wait for FEMA approval and environmental clearance before any work begins.
  2. Budget Against the Cap: Plan around the lesser of the federal share of the original restoration estimate or of actual costs; mitigation in the original scope is dropped from the cap.
  3. Keep Projects Out of Regulatory Floodways: Ensure any new facility or equipment site is entirely outside designated regulatory floodways.
  4. Maintain Flood Insurance for Floodplain Placements: Obtain and maintain flood insurance if the approved alternate project is built in a flood hazard area.
  5. Stop Temporary Facility Costs: Temporary facility funding ends when you request an alternate project, so time the request with your interim operations in mind.
Govstar summarizes FEMA’s Public Assistance Program and Policy Guide in plain language and links to the official text. Govstar is independent and not affiliated with FEMA. This is general guidance, not legal advice.