Yes, if a licensed engineer, architect or certified cost estimator prepares it on unit costs (not a lump sum), certifies it matches the agreed damage, and it is detailed and reasonable. When FEMA writes the estimate for a large permanent work site less than 90 percent complete, it uses the Cost Estimating Format (CEF). Either way, FEMA reduces the estimate for actual or expected insurance proceeds.
A unit-cost estimate signed by a licensed professional engineer, licensed architect or certified professional cost estimator, with a certification that it was prepared to industry standards and corresponds directly to repairing the agreed damage; the current design or construction phase and known costs; actual costs for work already done; and your insurance policies and any proceeds.
A lump-sum estimate is the quickest way to have yours rejected. Build in foreseeable contingencies such as security and staging, because FEMA judges reasonableness line by line under the Chapter 6 reasonable cost rules.
FEMA uses the Cost Estimating Format (CEF) to determine the total cost of large Public Assistance construction projects. The CEF is a uniform, forward-pricing model that mirrors the commercial applicant, general contractor and subcontractor relationship. It relies on a clearly defined, eligible scope of work and applies to permanent work sites less than 90 percent complete whose total costs are expected to meet the large project threshold. The CEF Instructional Guide sets the factor ranges, and only FEMA Headquarters can approve factors outside them.
The CEF breaks estimates into eight parts: