Yes. Administering and enforcing building codes and floodplain ordinances for disaster-damaged structures, public, private and residential, is eligible from the start of the incident period through 180 days after the declaration is amended to authorize permanent work. There are no extensions.
Small projects: a list of activities and number of locations. Large projects: activity logs or sign-ins, locations with addresses or GPS, and rights-of-entry where needed. Source: PAPPG Table 30.
Start the 180-day clock tracking on day one. Surge permitting and substantial damage work often runs past the window, and FEMA won’t extend it.