Small projects need an itemized summary by contractor. Large projects need the full procurement file plus invoices, and time-and-materials contracts need proof of close oversight.
All small projects must still comply with procurement rules, and FEMA reviews any small project using noncompetitive, time-and-materials or cost-plus-percentage contracts.
Source: PAPPG Table 15.
Build the procurement file as you go. Selection memos and price analyses written after FEMA asks for them rarely hold up.
FEMA’s Procurement Under Grants Policy Guide requires local governments and nonprofits to keep records detailing the history of every procurement: the rationale for the method, the selection of contract type, the contractor selection or rejection, and the basis for the price, along with the signed contract and every signed modification.
Keep the records for three years from submission of the final expenditure report, longer if litigation, claims or audit findings are open. Missing clauses are among the most common findings, so confirm each contract contains the Appendix II provisions it needs.
Full guide: use the Clause Checklist and “Standards & Conflicts” section of GovStar’s Procurement and Contracting Guide.