Manage Costs & Resources › Cost Eligibility

Can we claim the cost of finding and inspecting disaster damage?

FEMA term
Surveys to assess or locate damage or debris impacts
Short answer

Surveying overall impacts and locating damage are not project costs, but can be claimed as management costs. Detailed inspections to determine the extent of damage and how to repair it are part of the project.

What FEMA requires

  • Assessing overall impacts, locating damage or debris, and preliminary damage assessments: eligible only as management costs.
  • Inspecting a facility where damage was found during a post-declaration survey: eligible as management costs if the facility is eligible.
  • Detailed inspections and professional evaluations to determine extent of damage, debris quantities and repair method: eligible as project costs.
  • For partially damaged systems, eligible inspection cost is proportional: inspect 500 feet of sewer and find 100 feet damaged, and one-fifth of the cost is eligible.

Documentation

Inspection reports, the length or area inspected versus damaged, and time and cost records.

Watch out · Govstar practitioner advice

Scope system-wide inspections (sewer, storm drains) carefully. FEMA pays only the damaged share, so a broad inspection can cost you more than it recovers.

GovStar deeper dive

Going further: how it works in practice

Practitioner explainers for this topic, with the takeaways that matter most.

Surveys to assess or locate damage and debris

Public Assistance applicants are responsible for identifying and documenting all locations of incident-related damage and debris. Costs of general, area-wide assessments—initial field surveys, mapping general debris zones, and taking part in Preliminary Damage Assessments (PDAs)—are indirect costs, eligible only under the Management Costs allowance. They cannot be claimed as direct project costs.

If a post-declaration survey finds specific damage to a particular facility, the inspection costs for that facility can be claimed as a direct cost, provided they are itemized and tracked to that project. Detailed follow-up inspections to define the repair scope or calculate debris quantities are eligible as part of the restoration or debris project. For partially damaged linear systems (such as a sewer or water line), inspection costs are prorated by the share of the system that was actually damaged. For example, if an applicant inspects 500 linear feet of sewer line and documents damage along 100 linear feet, only 20% (one-fifth) of the inspection cost is eligible.

Key takeaways

  1. Keep Area-Wide Scouting Off Project Worksheets: Charge widespread damage scouting and initial debris surveys to management costs rather than individual projects.
  2. Track Facility Inspections to Projects: Route structure-specific inspection costs to that facility's project so they can be claimed as direct costs.
  3. Prorate Linear Utility Inspections: Document the total footage inspected and reduce the claimed inspection cost in proportion to the damaged portion.
  4. Use FEMA 352 for Seismic Screenings: Follow FEMA 352 when inspecting post-earthquake damage to welded steel moment-frame buildings.
  5. Separate Rapid Safety Placarding from Damage Appraisals: Document rapid life-safety screenings ("red-tagging") as short-term Category B actions, separate from engineering repair assessments.
Govstar summarizes FEMA’s Public Assistance Program and Policy Guide in plain language and links to the official text. Govstar is independent and not affiliated with FEMA. This is general guidance, not legal advice.