FEMA term
EHP laws: greensheet; NEPA; NHPA Section 106; Endangered Species Act
Short answer

The greensheet is FEMA’s disaster-specific EHP guide, prepared at the start of each declaration for your state and area. The three core reviews: NEPA requires FEMA to weigh environmental impacts and alternatives; Section 106 requires FEMA to consider effects on historic properties and consult the historic preservation officer; and the Endangered Species Act requires consultation with wildlife agencies to protect listed species and habitat.

What FEMA requires

  • FEMA reviews every PA project for compliance with applicable federal EHP laws, regulations and executive orders. Compliance with all federal, state, local, tribal and territorial laws is a requirement of every FEMA award; local laws such as hazardous materials rules vary and aren’t listed in Appendix D.
  • Greensheet: FEMA’s disaster-specific EHP guidance, prepared at the start of each declaration, covering relevant laws, triggering project types, and federal and local laws to follow.
  • NEPA: FEMA must consider environmental impacts and reasonable alternatives, with public involvement, under DHS procedures. The PAPPG notes that, effective April 11, 2025, an interim final rule removed the Council on Environmental Quality’s NEPA implementing regulations.
  • NHPA Section 106: FEMA consults the SHPO or THPO and other consulting parties, often through programmatic agreements, and resolves adverse effects through avoidance, minimization or compensation.
  • Endangered Species Act: FEMA consults the U.S. Fish and Wildlife Service and NOAA Fisheries so projects don’t jeopardize listed species or destroy or adversely modify critical habitat.
<table class="pt-table"><thead><tr><th>Law</th><th>What it requires</th><th>Who FEMA consults</th></tr></thead><tbody><tr><td>NEPA</td><td>Consider environmental impacts of the project and reasonable alternatives before deciding, with public involvement</td><td>Follows DHS procedures</td></tr><tr><td>NHPA Section 106</td><td>Consider effects on historic properties (on or eligible for the National Register) and resolve adverse effects</td><td>SHPO or THPO, other consulting parties, Advisory Council on Historic Preservation</td></tr><tr><td>Endangered Species Act</td><td>Ensure projects don’t jeopardize listed species or harm critical habitat</td><td>U.S. Fish and Wildlife Service, NOAA Fisheries</td></tr></tbody></table>

Documentation

The greensheet for your declaration, information on historic properties affected (age, renovations, register listings), and any species or habitat information for the work sites.

Watch out · Govstar practitioner advice

Ask for your declaration’s greensheet early. It tells you which laws and project types are likely to trigger review in your area, and it is the fastest way to spot permit needs before work starts.

GovStar deeper dive

Going further: how it works in practice

Practitioner explainers for this topic, with the takeaways that matter most.

National Historic Preservation Act (NHPA)

Section 106 of the NHPA requires federal agencies to consider project effects on historic properties (districts, structures, landscapes, archaeological sites) listed in or eligible for the National Register of Historic Places. FEMA identifies these properties within a project's Area of Potential Effect (APE) and consults with the SHPO or THPO. Physical work should not proceed until the review is complete.

Key takeaways

  1. Hold Construction Pending Section 106 Completion: Avoid ground disturbance or structural alterations on a property that may be historic (FEMA commonly screens buildings 45 years or older) until the review is complete.
  2. Map Undisturbed Ground Early: Identify whether any project footprint crosses previously undisturbed soils, since those areas often need archaeological evaluation.
  3. Use Programmatic Agreements: Review your state’s FEMA programmatic agreement to find work types that can be cleared without individual SHPO or THPO consultation.
  4. Define a Precise Area of Potential Effect (APE): Document the full APE, including staging areas and access roads, to help FEMA identify historic properties faster.
  5. Build Treatment Conditions into Your Scope: Expect consultation to add conditions, such as in-kind materials or archaeological monitoring, and include them in your scope and cost estimate.

Endangered Species Act (ESA)

Section 7 of the ESA requires federal agencies to conserve listed threatened and endangered species and protect designated critical habitat. FEMA consults the U.S. Fish and Wildlife Service (USFWS) or NOAA Fisheries when a project may affect listed species.

Even if a project qualifies for a statutory exclusion from NEPA review, FEMA must still meet ESA requirements. Applicants must give FEMA time to complete these reviews before starting physical work; failing to do so puts funding at risk.

Key takeaways

  1. Treat ESA as Separate from NEPA: Never assume a project is cleared because it is exempt from NEPA; ESA review still applies.
  2. Build Review Time into Schedules: Allow time in recovery timelines for FEMA to complete any consultation before mobilization.
  3. Flag Culvert and Drainage Work for Fish Habitat Reviews: Flag drainage, bridge scour and culvert replacement designs for species review early.
  4. Identify Undisturbed Ground Upfront: Flag staging areas, access roads and alternate project sites that cross previously undisturbed ground.
  5. Include Stop-Work Clauses for Wildlife Encounters: Require contractors to stop work immediately if a listed species is sighted in the work area, and follow any consultation conditions.