Clean Water Act; Rivers and Harbors Act; Safe Drinking Water Act
Short answer

The Clean Water Act requires Corps of Engineers or state permits before you discharge into, dredge or fill waters, which commonly includes bridge, stream crossing, dock, pier and marina repairs. The Rivers and Harbors Act requires Corps authorization for structures in or over navigable waters. The Safe Drinking Water Act requires FEMA to consult EPA for projects that could contaminate a sole source aquifer.

What FEMA requires

  • Clean Water Act: regulates pollutant discharges to waters of the United States (rivers, streams, lakes, ponds, coastlines, wetlands, estuaries) and sets surface water quality standards. Discharges into navigable waters require permits from the Corps or the state, and dredging or filling in waters requires authorization.
  • You must acquire applicable permits before beginning work and give FEMA documentation, which may include nationwide permit compliance statements or individual Section 404 permits.
  • Rivers and Harbors Act: Corps authorization is required to build any structure in or over navigable water, including bridges, causeways, dams and dikes; usually handled with the Section 404 request.
  • Safe Drinking Water Act: EPA may designate sole source aquifers. FEMA must consult EPA before funding a project in a sole source aquifer review area that could contaminate it.
<table class="pt-table"><thead><tr><th>Law</th><th>Triggered by</th><th>What you need</th></tr></thead><tbody><tr><td>Clean Water Act</td><td>Discharges into waters of the U.S.; dredging or filling in waters; bridges, stream crossings, docks, piers, marinas</td><td>Corps or state permits before work starts; nationwide permit compliance statements or individual Section 404 permits</td></tr><tr><td>Rivers and Harbors Act</td><td>Any structure in or over navigable water, including bridges, causeways, dams, dikes, docks, piers and marinas</td><td>Corps authorization, usually handled with the Section 404 request</td></tr><tr><td>Safe Drinking Water Act</td><td>Projects that could contaminate a sole source aquifer, in its review area</td><td>FEMA consults EPA before funding</td></tr></tbody></table>

Documentation

Section 404 individual permits or statements of compliance with nationwide permits, Rivers and Harbors Act authorizations, state water permits, and information on whether the project is in a sole source aquifer review area.

Watch out · Govstar practitioner advice

Get the permit before the excavator goes in the water. Appendix D says permits must be acquired before work begins and documented to FEMA; work done without them can lose its funding.

GovStar deeper dive

Going further: how it works in practice

Practitioner explainers for this topic, with the takeaways that matter most.

Waters of the United States

Any project involving construction in or next to waters of the United States, which can include streams (even intermittent ones), drainage ditches, lakes, ponds and adjacent wetlands, can affect water quality. FEMA’s environmental review looks closely at any construction in or near a water body.

Applicants can check 1:24,000 scale USGS topographic maps or ask the U.S. Army Corps of Engineers (USACE) for a jurisdictional determination. Culvert realignments, channel widening, bridge repairs and pond excavation near water typically need Corps or state permits under the Clean Water Act, obtained before work begins.

Key takeaways

  1. Flag Work Near Water Early: Identify any construction or staging in or near a waterway or wetland at project formulation so EHP review starts early.
  2. Use Topographic Maps and Site Visits: Use 1:24,000 scale USGS topographic maps, along with wetland inventories and site visits, to identify minor or intermittent water bodies.
  3. Request a USACE Jurisdictional Determination: Where it is unclear whether a water body is regulated, ask the Corps for a determination for your project area.
  4. Get Permits Before Work Starts: Obtain nationwide permit compliance statements or individual Section 404 permits before construction, and give copies to FEMA.
  5. Include Sediment Controls in Project Scopes: Include line items for silt fencing, turbidity curtains and erosion control blankets in repair scopes for culverts and bridges.