Short answer
After the initial grouping, FEMA splits out sites that would slow down or complicate the rest: complex environmental reviews, flood zones, sites needing design or studies, facilities with all work complete, complex facilities, possible ineligible work, and oversized projects. All Category I code and floodplain work goes in one project, and all Category Z management costs go in one project.
<table class="pt-table"><thead><tr><th>Separate the site or facility if it…</th><th>Why</th></tr></thead><tbody><tr><td>Needs a complex environmental or historic review</td><td>So the review doesn’t hold up the rest</td></tr><tr><td>Is in a special flood hazard area</td><td>Floodplain requirements apply</td></tr><tr><td>Needs design or studies to decide how to restore it</td><td>FEMA amends the project once the repair is set</td></tr><tr><td>Has 100 percent of its work complete</td><td>Completed work is handled differently</td></tr><tr><td>Is complex and needs specialized technical support</td><td>For example wastewater plants, dams, hospitals, schools</td></tr><tr><td>Potentially has ineligible work</td><td>Keeps disputes contained</td></tr><tr><td>Would make a project too burdensome to review</td><td>Too many sites in one project</td></tr><tr><td>Is agreed by you and FEMA to be illogical to combine</td><td>Specific circumstances</td></tr></tbody></table>
Information that shows why a site should stand alone: its flood zone status, any expected environmental or historic issues, whether design or studies are needed, and whether all work on the facility is complete.
Watch out · Govstar practitioner advice
A facility can only be split out as “complete” if all its work is complete. You can’t separate the finished parts of one facility from the unfinished parts. Private nonprofits should keep critical service facilities in separate projects so they aren’t held up waiting on the SBA loan determination.