FEMA must avoid floodplains and wetlands when practicable alternatives exist, using its 8-step decision process for projects over $18,000. New construction is barred in coastal high hazard areas and floodways, and critical facilities must consider the 500-year floodplain.
Floodplain maps, permits, any H&H study by a licensed engineer, and the alternatives analysis.
Flag floodplain sites at the start. The 8-step review and any H&H study take time, and starting work first can cost the funding.
Temporary critical facilities, such as field hospitals, medical sheltering or mortuary operations, often house people who can’t easily evacuate during a flood. For these critical actions, FEMA uses the 0.2-percent-annual-chance (500-year) floodplain, so sites should avoid the Special Flood Hazard Area and the 500-year floodplain (Zones V, A and shaded X). If no practicable alternative exists, the facility needs higher protection and a formal flood evacuation plan.