Within 60 days of your recovery scoping meeting. FEMA may extend it if you ask in writing and justify it with circumstances beyond your or the recipient’s control, such as a site you can’t reach, or new categories of work approved after your meeting. Roads still under water may also get more time so they can be assessed once the water recedes and the soil dries.
The date of your recovery scoping meeting, the date you submitted the impact list, and for any extension, a written request with the justification and evidence (for example, photos or reports showing a site was still inaccessible or under water).
The 60 days start at the recovery scoping meeting, not when you finish assessing. Request any extension before the deadline, in writing, with the specific sites and the reason each one could not be assessed.