Yes, as an improved project, if the facility keeps its pre-disaster function. FEMA’s funding is capped at the lesser of the federal share of the approved restoration estimate or the federal share of your actual costs.
Recipient approval, the capped restoration estimate, and the improved project scope and actual costs.
Decide on an improved project before formulation if you can. Converting an obligated project later caps that site and slows everything around it.
Improved Projects allow applicants to incorporate improvements (for example, paving a gravel road or adding a bay to a firehouse) while restoring pre-disaster function. The recipient (usually the state) must approve them before construction, and FEMA reviews environmental compliance if the configuration changes significantly. Federal funding is capped at the lesser of the federal share of the approved restoration estimate or the federal share of actual costs. Applicants bear full responsibility for the balance of improvement costs.