Will FEMA pay for the cost of managing our FEMA grant?

FEMA term
Category Z: Management costs
Short answer

Yes, as management costs: actual costs up to 5 percent of a subrecipient’s total award, and up to 7 percent of the total award for recipients. They cover indirect and direct administrative costs of developing and managing eligible PA projects.

What FEMA requires

  • Costs must be associated with eligible facilities, work and costs.
  • Costs to survey overall impacts, locate damage or conduct preliminary damage assessments are management costs, not project costs.

Documentation

A summary of work and costs: number of employees, equipment used with rates, total labor and equipment hours (or miles), total costs, and a general description of tasks performed. FEMA may ask for more.

Watch out · Govstar practitioner advice

Track grant administration time from day one under its own charge code. It is the easiest cost to lose because nobody records it.

GovStar deeper dive

Going further: how it works in practice

Practitioner explainers for this topic, with the takeaways that matter most.

Management costs

The Disaster Recovery Reform Act of 2018 (DRRA) reshaped how administrative expenses are reimbursed by expanding Management Costs to include both direct and indirect administrative expenses. Under Section 1215 of the DRRA, FEMA replaced the older administrative allowances with a percentage-based framework that gives state and local governments more financial flexibility.

The statutory caps are:

  • Public Assistance (PA) Management Costs: up to 12% of the total award: up to 7% for the Recipient (the State) and up to 5% for the Subrecipient (the local applicant).
  • Hazard Mitigation Grant Program (HMGP) Management Costs: up to 15% of the total mitigation award: up to 10% for the Recipient and 5% for the Subrecipient.

Recipients and subrecipients must follow FEMA's management cost procedures for selecting options and documenting costs within the required timeframes, so claims are documented, verified, and processed uniformly.

Key takeaways

  1. Budget Within the 5% Subrecipient Cap: Plan and track your internal administrative and grant management activities around the 5% subrecipient cap for PA and HMGP.
  2. Combine Direct and Indirect Administrative Expenses: Capture both direct project management hours and indirect administrative overhead under the management cost allowance authorized by DRRA Section 1215.
  3. Meet the Option Selection Deadlines: File your management cost selections within the timeframes FEMA and your recipient set after the declaration.
  4. Follow the Management Cost Procedures: Set up financial tracking that mirrors FEMA's Public Assistance management cost documentation and processing rules.
  5. Keep Management Costs Separate from Project Costs: Track administrative management costs apart from your project costs to avoid duplicate claims and to stay compliant at closeout.