Chapter 10 › I.D Navigating the EHP Compliance Process

How can we get through the EHP review faster?

FEMA term
Navigating the EHP compliance process
Short answer

Give EHP a complete, clear scope of work with maps, photos and site plans; get permits before construction; share any permits you already hold, which can speed the review; keep and attach all agency correspondence; and follow permit conditions and best management practices, then document that you did.

What FEMA requires

  • Provide a complete and clear scope of work to minimize clarification requests.
  • Provide maps or sketches, photos, site plans and descriptions of pre-disaster conditions and the proposed or completed work.
  • Obtain necessary permits and authorizations before construction.
  • Provide pre-existing permits and authorizations; FEMA may be able to expedite review based on them.
  • Keep copies of all correspondence with federal or state agencies about permits and attach them to the grant application.
  • Follow permit and authorization conditions and best management practices, and verify conditions were met if the work is complete.

Documentation

Maps, sketches, photos and site plans of pre-disaster conditions and the work; existing permits and authorizations; copies of all correspondence with federal and state agencies, attached to the grant application; and records showing permit conditions and best management practices were met.

Watch out · Govstar practitioner advice

Get permits before you build. Starting construction without required permits or authorizations puts the funding for that work at risk, and after-the-fact fixes are slow and uncertain.