Rebuild & Mitigate › Permanent Work

What does FEMA pay to rebuild or repair a damaged facility?

FEMA term
Permanent work (Categories C–G); pre-disaster design and function
Short answer

Permanent work restores a facility to its pre-disaster design (size and capacity) and function, in line with applicable codes and standards. The facility itself must be eligible, and insurable facilities must then be insured.

What FEMA requires

  • Pre-disaster design is the size or capacity as built or later modified, not how much you were using it. A school designed for 100 students is restored for 100, even if more attended.
  • Pre-disaster function is the use it was designed or formally altered for. If it served a different use without being altered, FEMA funds whichever restoration costs less.
  • Work must comply with environmental and historic preservation requirements.
  • Categories: C roads and bridges; D water control; E buildings and equipment; F utilities; G parks, recreational and other.

Documentation

Design documents or records of later modifications showing the facility’s capacity and function.

Watch out · Govstar practitioner advice

Find the as-built drawings early. Without them, proving capacity or function beyond what FEMA sees on site is hard.

GovStar deeper dive

Going further: how it works in practice

Practitioner explainers for this topic, with the takeaways that matter most.

Restoring to pre-disaster design and function

FEMA provides Public Assistance funding to return damaged public infrastructure and eligible Private Nonprofit buildings to their pre-disaster condition. The core standard is a "no-expansion" rule: funding is limited to restoring components so they match the pre-disaster design (the size or capacity as built or formally modified, not how much it was used) and function. Permanent work covers Categories C (roads and bridges), D (water control), E (buildings and equipment), F (utilities) and G (parks, recreational and other).

Exceptions are allowed when a modification is required by an eligible, uniformly enforced code or standard. Projects that add eligible Section 406 hazard mitigation measures, such as wind-resistant utility poles or elevated mechanical systems, can receive additional funding for future resilience.

Key takeaways

  1. Establish a Clear Pre-Disaster Design Baseline: Archive engineering drawings, structural schematics, and capacity ratings for all major public assets to prove the pre-incident starting point.
  2. Prove Consistent, Uniform Enforcement of Building Codes: Maintain documentation showing that any code upgrades applied to a project come from a written code or standard your agency enforces uniformly.
  3. Isolate Mitigation Additions onto a Section 406 Ledger: Separate any cost-effective resiliency enhancements from basic repair items, ensuring they are explicitly requested as Section 406 Hazard Mitigation elements.
  4. Keep Capacity Expansions Off Standard Repair Projects: Do not increase the physical footprint or capacity of a facility on a standard restoration project without requesting an Improved Project.
  5. Apply the Right PAPPG Version: Check your restoration plan against the PAPPG version in effect for your declaration date; v5.0 applies to incidents declared on or after January 6, 2025.
Govstar summarizes FEMA’s Public Assistance Program and Policy Guide in plain language and links to the official text. Govstar is independent and not affiliated with FEMA. This is general guidance, not legal advice.