Pre-positioned (standby) contracts work if they were competed under federal rules and cover the work performed. FEMA advises against cooperative purchasing and piggyback contracts because they often fail federal procurement requirements.
FEMA reimburses reasonable costs under a pre-positioned contract if:
If you use a cooperative purchasing program, you must document how its use complied with all procurement requirements. Joint procurements, where two or more entities run one solicitation together, see fewer compliance problems.
The original solicitation and award for any pre-positioned contract, and a written compliance analysis for any cooperative purchase.
A piggyback contract was competed for someone else’s needs, so its scope rarely matches yours. Compete your own pre-positioned contracts before disaster season.
Prepositioned contracts for debris removal, generators and other recurring needs should be competed before disaster season, outside the pressure of an incident, and scoped for the size of event you may face. Work beyond that scope is a cardinal change that FEMA treats as a new sole-source award.
Joint procurements, where two or more entities solicit and award together from the start, are encouraged. Piggybacking on another jurisdiction’s contract is discouraged; it is acceptable only if the original contract was procured under the standards that apply to you, allows assignment, covers your work without cardinal changes, and has a fair and reasonable price. Otherwise FEMA treats a local government’s or nonprofit’s piggyback contract as noncompetitive.