Short answer
A facility is repairable if the repair cost is 50 percent or less of the replacement cost and it can be repaired to work as well as before. Above 50 percent, or if repair isn’t feasible, replacement is eligible.
<table class="pt-table"><thead><tr><th>Cost</th><th>Repair estimate (numerator)</th><th>Replacement estimate (denominator)</th></tr></thead><tbody><tr><td>Repair of disaster damage, with codes for the damaged elements</td><td>Included</td><td>—</td></tr><tr><td>Replacement to pre-disaster size, capacity and function, with codes</td><td>—</td><td>Included</td></tr><tr><td>Upgrades to undamaged elements (e.g. elevating the whole facility)</td><td>Excluded</td><td>—</td></tr><tr><td>Floodplain elevation or floodproofing of a substantially damaged facility</td><td>Excluded</td><td>Included</td></tr><tr><td>Demolition</td><td>Only selective demolition needed for the repair</td><td>Excluded</td></tr><tr><td>Site work, soft costs, contents, mitigation, emergency work</td><td>Excluded</td><td>Excluded</td></tr></tbody></table>
Repair and replacement estimates prepared to FEMA’s estimating requirements, with the calculation and any feasibility study.
Watch out · Govstar practitioner advice
Build both estimates using the same exclusions FEMA uses. Including site work or soft costs in your repair number is the most common miscalculation.