Chapter 8 › III. Hazard Mitigation

Can FEMA pay to make our facility stronger than before?

FEMA term
PA hazard mitigation (Section 406)
Short answer

Yes, through PA hazard mitigation, which funds cost-effective measures beyond codes and standards that reduce future damage to the damaged parts of a facility. It applies only to permanent work projects (Categories C–G), not emergency work.

What FEMA requires

  • Measures must directly reduce future damage to the damaged portion of the facility, be technically feasible, comply with environmental and historic requirements, and not create new hazards.
  • Separate measures, such as floodwalls, new drainage along a damaged road, defensible space, or dry floodproofing of interdependent buildings, can qualify if they protect the damaged portion.
  • Code-required upgrades are not mitigation; mitigation is the work above code.
  • Engineering and design to develop a mitigation proposal are eligible if included in the approved scope.
  • If you don’t complete approved mitigation, FEMA deobligates it. PA and HMGP funds can be used on the same facility, but not for the same work.
  • Mitigation done after a quick repair, or before FEMA could review it, can still be eligible if cost-effective and environmentally compliant.
<table class="pt-table"><thead><tr><th>A 406 measure is cost-effective if…</th><th>Basis</th></tr></thead><tbody><tr><td>Its cost is no more than 15% of the facility’s eligible repair cost (before insurance reductions)</td><td>15 percent rule</td></tr><tr><td>It is listed in PAPPG Appendix J and costs no more than 100% of the eligible repair cost</td><td>Pre-approved measures</td></tr><tr><td>A benefit-cost analysis using FEMA’s BCA Toolkit shows benefits exceed costs</td><td>Benefit-cost analysis</td></tr></tbody></table>

Documentation

A hazard mitigation proposal with scope, cost, cost-effectiveness basis and environmental information.

Watch out · Govstar practitioner advice

Raise mitigation at the first site inspection. Once a project is obligated without it, adding mitigation takes far longer.