Section 705 limits that. Except for fraud, FEMA must give notice of intent to recover funds from a government recipient or subrecipient within 3 years of the recipient’s certification of project completion. Even within 3 years, FEMA can’t recover funds when the payment meets Section 705’s conditions. It doesn’t protect private nonprofits.
The completion certification date, the approved project documents, and evidence costs were reasonable and the work achieved its purpose.
In second-appeal decisions, Section 705 claims most often fail on timeliness (including late recipient transmittals), nonprofit status, or noncompliance that means the purpose wasn’t accomplished, such as unapproved scope changes, work started before environmental review, or procurement violations.