Cost overruns
Public Assistance cost estimates are often approved before work is finished. When actual costs exceed the approved estimate, the difference is a cost overrun. Overruns usually come from hidden damage found after approval, changes in unit prices for labor and materials, scope changes during the work, or unavoidable delays.
FEMA handles overruns differently by project size:
- Large Projects: Evaluate the overrun and submit a request for additional funding through the recipient to FEMA as soon as possible. If additional work or hidden damage is found during construction, notify the recipient and FEMA before performing the work so FEMA can inspect if needed. Requests must be backed by documentation showing the extra costs are for eligible work.
- Small Projects: Overruns are not reviewed one project at a time. If the actual cost of all your small projects together exceeds the total obligated for them, you can file a single appeal for the net overrun. Submit it through the recipient within 60 days of the latest work completion date of all your small projects (or of the last small project’s obligation, if later), with actual cost documentation for every small project, including both overruns and underruns.
Key takeaways
- Know Which Procedure Applies: Large project overruns are requested project by project; small project overruns go in one net overrun appeal covering all your small projects.
- Meet the Small Project Appeal Window: Submit any net small project overrun appeal within 60 days of the latest completion date of all your small projects, or of the last small project’s obligation if that is later.
- Notify FEMA Before Doing New Work: If hidden damage or a needed scope change appears during construction on a large project, notify the recipient and FEMA before doing the work.
- Reconcile Every Line Item: For a net overrun appeal, provide actual cost documentation for every small project, explaining both overruns and underruns.
- Document Causes of Delays and Price Changes: Show that cost increases from market prices or delays were reasonable and tied to the approved eligible work.