Final Reconciliation and Closeout

How FEMA Public Assistance projects and awards are closed: small project closeout and net small project overruns, large project closeout and its deadlines, the Section 705 limits on FEMA recovering funds, subrecipient and award closeout, and how long to keep your records. Every section is written as the question applicants actually ask, with FEMA’s requirements, the records you need, and the exact PAPPG pages.

5 topicsLarge projects: cost documents within 90 days of completionSection 705: 3-year limit on recovering fundsKeep records 3 years after the final expenditure report
Jump to a part of the chapter
Visual overview

Chapter 12 at a glance

GovStar visual overview
FEMA PA Award Closeout & Reconciliation Rules

Final reconciliation procedures, small project overruns, closeout packages, and Section 705 recovery limits.

Open the full overview →
Chapter 12 › IV. Documentation Retention Requirements

How long do we have to keep our FEMA project records?

Documentation retention requirements
p. 258
Short answer
Subrecipients must keep all source documentation for each project for 3 years after the final expenditure report is transmitted. Recipients keep financial and program records for 3 years after submitting the final SF-425. Longer periods apply for property, audits, litigation and some state laws.
What FEMA requires
  • Retention can be longer for real property and equipment disposition, open audits or litigation.
  • State, local, tribal or territorial law may require longer retention.
  • For small projects under simplified procedures, keep source records for 3 years after the recipient certifies your last small project.
Documentation

A retention schedule by disaster and project, tied to the final expenditure report and SF-425 dates.

Watch out · Govstar advice
Retention runs from the end of the grant, not the disaster. Set retention by project, because a large disaster can stay open for many years.
PAPPG v5.0 p. 258 · 2 CFR 200.302, 200.334
Read this in the PAPPG
Chapter 12 › I.C, III Subrecipients; Public Assistance Award Closeout

How does the whole disaster grant get closed out?

Subrecipient closeout; Public Assistance award closeout
pp. 257–258
Short answer
Once all of a subrecipient’s projects are closed and no audits are pending, the recipient asks FEMA to close that subrecipient. The recipient then closes the whole PA award with a final Federal Financial Report (SF-425).
What FEMA requires
  • The subrecipient closeout request includes a project completion certification report listing every project.
  • FEMA closes the award once all appeals have final determinations, all eligible funds are obligated, all projects are closed, funds are passed through and reported, and administrative actions are complete.
  • Recipients must liquidate all obligations within 120 days after the award’s period of performance ends, unless FEMA grants a written extension.
Documentation

Project completion certification report, final expenditure report, and the final SF-425.

Watch out · Govstar advice
Open appeals hold the entire award open. Resolve or withdraw stale appeals so the rest of the disaster can close.
PAPPG v5.0 pp. 257–258 · 2 CFR 200.344
Read this in the PAPPG
Chapter 12 › II. Stafford Act Section 705

Can FEMA take money back years after a project closes?

Stafford Act Section 705
p. 257
Short answer
Section 705 limits that. Except for fraud, FEMA must give notice of intent to recover funds from a government recipient or subrecipient within 3 years of the recipient’s certification of project completion. Even within 3 years, FEMA can’t recover funds when the payment meets Section 705’s conditions. It doesn’t protect private nonprofits.
What FEMA requires
  • The 3-year clock runs from the date the recipient submitted the certification of project completion to FEMA.
  • Within 3 years, Section 705(c) bars recovery when the payment was authorized by an approved agreement, the costs were reasonable, and the purpose of the grant was accomplished.
  • Details are in FEMA Recovery Policy FP 205-081-2, Stafford Act Section 705, Disaster Grant Closeout Procedures.
  • Appeal deadlines still apply to Section 705 claims.
Documentation

The completion certification date, the approved project documents, and evidence costs were reasonable and the work achieved its purpose.

Watch out · Govstar advice
In second-appeal decisions, Section 705 claims most often fail on timeliness (including late recipient transmittals), nonprofit status, or noncompliance that means the purpose wasn’t accomplished, such as unapproved scope changes, work started before environmental review, or procurement violations.
PAPPG v5.0 p. 257 · Stafford Act § 705 · FP 205-081-2
Read this in the PAPPG
Chapter 12 › I.B Large Projects

What does FEMA need to close out a large project?

Large project reconciliation and closeout
pp. 254–257
Short answer
Large projects are paid on actual documented costs (except capped projects). You must provide cost documentation within 90 days of work completion, and the recipient must certify completion and submit the final claim within 180 days of completion or the project deadline, whichever comes first.
What FEMA requires
  • If work finished before obligation, the 90- and 180-day clocks start at obligation.
  • Before closing, FEMA confirms there are no open appeals, audits or arbitrations; checks that work matched the approved scope (including mitigation) and finished within the deadline; rules out duplicate funding; and validates cost principles and award terms such as codes, environmental and historic compliance, civil rights and insurance.
  • Reviews already done for projects obligated at 100 percent complete on actual costs aren’t repeated.
  • Unfinished mitigation turns the project into an improved project, which may be capped or deobligated.
  • Capped projects must show the funds were used as allowed.
Documentation
  • Final inspection report, scope and expenditure summaries, and cost backup (labor, equipment, materials and contracts).
  • Procurement documents, mutual aid agreements, insurance final statement of loss, regulatory correspondence, change orders and pay policies.
  • All codes and standards used, proof of compliance with award terms, and photos of completed permanent work (Categories C–G).

Source: PAPPG Table 34.

Watch out · Govstar advice
Build the closeout file as the project runs. Reconstructing invoices, change orders and procurement records years later is where large-project deobligations come from.
PAPPG v5.0 pp. 254–257 · 44 CFR 206.205(b)
Read this in the PAPPG
Chapter 12 › I.A Small Projects

How do small projects close out, and can we recover costs that ran over?

Small project closeout; net small project overrun (NSPO)
pp. 253–254
Short answer
Small projects are funded on estimates and close with a completion certification. FEMA adjusts them only for specific reasons. If your small projects together cost more than FEMA obligated, you can request the difference through a net small project overrun appeal.
What FEMA requires
  • FEMA adjusts an obligated small project only for: incomplete scope, approved scope changes (including added mitigation), insurance or other funds differing from what was deducted, errors or omissions, hidden damage, noncompliance, or fraud, waste or abuse. Only the affected items change.
  • Overrun appeal: file within 60 days of the latest work completion date of all your small projects (or of the last small project’s obligation, if later), with actual cost documentation for every small project.
  • Completion certification (if not filing an overrun appeal): due to the recipient within 90 days of the last small project’s completion or approved deadline, whichever is sooner; from obligation if work finished earlier.
Documentation

Actual costs for all small projects (for an overrun), or the completion certification.

Watch out · Govstar advice
The overrun is calculated across all your small projects together, not project by project. Track actual costs on every small project, including ones that came in under estimate.
PAPPG v5.0 pp. 253–254 · 44 CFR 206.204(e)
Read this in the PAPPG
Govstar summarizes FEMA’s Public Assistance Program and Policy Guide, version 5.0 Amended, for disasters declared on or after January 6, 2025. “Watch out” notes are Govstar practitioner advice, not FEMA policy. Govstar is independent and not affiliated with FEMA. This is general guidance, not legal advice.