Home / Laws & Policy / PAPPG chapters / Chapter 2
PAPPG v5.0 · Chapter 2 · pages 40–44

Coordination and Appeal Rights

How FEMA reviews eligibility and tells you its decisions, and what to do when you disagree: the eligibility building blocks and simplified procedures, requests for information and determination memos, your appeal rights and what an appeal must contain, the filing deadlines, and arbitration before the Civilian Board of Contract Appeals. Every section is written as the question applicants actually ask, with FEMA’s requirements, the records you need, and the exact PAPPG pages.

5 topicsAppeal within 60 days of FEMA’s determinationRFI deadlines: at least 15 daysArbitration if over $500,000 is in dispute ($100,000 rural)
Jump to a part of the chapter
Visual overview

Chapter 2 at a glance

GovStar visual overview
Eligibility & Appeal Rights Framework

Master the PA eligibility pyramid, RFI deadlines, two-tiered appeals, and CBCA arbitration thresholds.

Chapter 2 › I.I Arbitration

Can we go to arbitration instead of a second appeal?

Arbitration (Stafford Act § 423)
p. 44
Short answer
Yes, if more than $500,000 is in dispute ($100,000 in rural areas), you filed a timely first appeal, and FEMA denied it or didn’t decide within 180 days. You choose arbitration or a second appeal, not both, and the Civilian Board of Contract Appeals (CBCA) decision is final.
What FEMA requires
  • Request arbitration by emailing the recipient, the CBCA and FEMA at the same time, within 60 days of FEMA transmitting the first appeal decision.
  • If FEMA hasn’t decided the first appeal within 180 days, withdraw it and request arbitration within 30 days of the withdrawal.
  • The CBCA charges no fee, but each side pays its own costs, such as attorneys, consultants, copying and travel. Those costs are not eligible for FEMA funding.
Documentation

The first appeal and its decision (or proof of 180 days with no decision), the amount in dispute, and the arbitration request sent to all three parties.

Watch out · Govstar advice
Weigh arbitration early. It is final, there’s no further appeal, and your representation costs are your own, so it works best for large, well-documented disputes.
PAPPG v5.0 p. 44 · 44 CFR 206.206(b)(3) · FEMA Policy 104-22-0001
Read this in the PAPPG
Chapter 2 › I.G–H Appeal Deadlines; Appeal Review and Decisions

What are the deadlines for appeals, and how fast does FEMA decide?

Appeal deadlines; appeal review and decisions
pp. 43–44
Short answer
You have 60 days from the date FEMA transmits a determination or first appeal decision to file with the recipient. The recipient has 120 days from that same date to forward it to FEMA with its recommendation. Miss either deadline and FEMA denies the appeal as untimely.
What FEMA requires
  • If day 60 or 120 falls on a weekend or federal holiday, the next business day counts.
  • FEMA reviews the appeal against the administrative record and the rules for that incident. It may send an RFI or ask independent experts for a technical review.
  • A second appeal decision is FEMA’s final administrative decision. A determination or first appeal decision you don’t appeal on time also becomes final.
<table class="pt-table"><thead><tr><th>Step</th><th>Deadline</th><th>Counted from</th></tr></thead><tbody><tr><td>Applicant files first or second appeal with the recipient</td><td>60 days</td><td>FEMA transmits the determination or first appeal decision</td></tr><tr><td>Recipient forwards the appeal to FEMA with its recommendation</td><td>120 days</td><td>The same FEMA transmittal date</td></tr><tr><td>FEMA issues its appeal decision</td><td>90 days</td><td>Receiving the appeal (or the requested information or technical review)</td></tr><tr><td>Responding to an RFI</td><td>At least 15 days, as set in the RFI</td><td>The date of the RFI</td></tr></tbody></table>
Documentation

Proof of the transmittal date, proof of when you filed with the recipient, and the recipient’s transmittal to FEMA.

Watch out · Govstar advice
Both deadlines run from FEMA’s transmittal date, not when you received or opened it. In FEMA’s second-appeal decisions, late forwarding by the recipient has repeatedly cost applicants their appeals, so track the recipient’s 120-day date too.
PAPPG v5.0 pp. 43–44 · 44 CFR 206.206(b)–(c)
Read this in the PAPPG
Chapter 2 › I.F Appeal Rights and Requirements

Can we appeal a FEMA decision, and what does the appeal need to include?

Appeal rights and requirements
pp. 42–43
Short answer
Yes. You can appeal any FEMA determination on your application, including eligibility denials and denied time extensions. The first appeal goes through the recipient to the Regional Administrator; a second appeal goes through the recipient to the Assistant Administrator for Recovery at FEMA Headquarters.
What FEMA requires
  • Appeals must be written and submitted electronically; recipients submit them to FEMA through Grants Portal.
  • Every appeal must include documented justification for your position, the specific amount in dispute for each issue, and the laws, regulations or policies (for that disaster) you believe FEMA’s decision conflicts with.
  • You may withdraw an appeal at any time with a written request sent to both the recipient and FEMA.
  • FEMA may raise new eligibility issues on appeal that weren’t in the original determination.
  • These procedures apply to disasters declared on or after January 1, 2022; older declarations follow the earlier appeal rules in 44 CFR 206.206.
Documentation

A written appeal with your argument, supporting documents, amounts in dispute by issue, and the specific citations.

Watch out · Govstar advice
Cite the rules in effect for your disaster’s declaration date. Citing current policy against an older disaster weakens an otherwise good argument.
PAPPG v5.0 pp. 42–43 · Stafford Act § 423 · 44 CFR 206.206
Read this in the PAPPG
Chapter 2 › I.C–E Facilitated Discussions; Requests for Information; Notification of an Ineligibility Determination

What happens when FEMA asks for more information or denies something?

Requests for information; notification of an ineligibility determination; facilitated discussions
pp. 41–42
Short answer
FEMA asks for missing information through a request for information (RFI) with a deadline of at least 15 days. Miss it without an approved extension and FEMA denies whatever it couldn’t verify. Any denial comes as a determination memo explaining what was denied, why, and how to appeal.
What FEMA requires
  • The RFI deadline depends on the volume and type of information requested, with a minimum of 15 days.
  • Ask for an extension before the deadline, through the recipient, if you need more time.
  • A determination memo must state what was denied and the amount, the legal or policy basis, and your appeal rights. It is sent electronically to you and the recipient.
  • Determinations can come from any part of the project, including Validate as You Go (VAYGo) audit findings.
  • If a dispute stalls, FEMA may offer a facilitated discussion led by an alternative dispute resolution specialist.
Documentation

Your complete RFI response, any extension request and approval, and the determination memo with its transmittal date.

Watch out · Govstar advice
Treat every RFI response as the first draft of your appeal. FEMA decides appeals on the administrative record, and the RFI response is usually its strongest piece.
PAPPG v5.0 pp. 41–42
Read this in the PAPPG
Chapter 2 › I.A–B PA Eligibility; Simplified Procedures; Sampling Procedures

How does FEMA decide what is eligible, and how much paperwork do we need?

PA eligibility pyramid; simplified procedures; sampling
pp. 40–41
Short answer
FEMA checks four building blocks in order: applicant, facility, work and cost. If any one can’t be shown, FEMA can’t fund it. Simplified procedures let small projects use summaries and self-certification, and FEMA can review a sample of large document sets instead of every page.
What FEMA requires
  • For governments, facility eligibility usually isn’t evaluated for debris removal and most emergency protective measures.
  • For private nonprofits, FEMA first confirms the nonprofit owns or operates a facility providing an eligible service.
  • Simplified procedures (Stafford Act § 422): small projects can submit summary documentation and self-certify. You must still keep all source records for 3 years after the recipient certifies your last small project complete.
  • Sampling: with large volumes of documents or damaged sites, you may submit summaries and FEMA validates a representative sample.
  • Terms like “must” and “required” in the PAPPG reflect legal requirements; missing them can jeopardize funding.
Documentation

Summary documentation for each building block, with full source records kept on file.

Watch out · Govstar advice
Self-certifying doesn’t mean you can discard backup. A later audit or closeout review will ask for the source records behind every certification.
PAPPG v5.0 pp. 40–41 · Stafford Act § 422
Read this in the PAPPG
Govstar summarizes FEMA’s Public Assistance Program and Policy Guide, version 5.0 Amended, for disasters declared on or after January 6, 2025. “Watch out” notes are Govstar practitioner advice, not FEMA policy. Govstar is independent and not affiliated with FEMA. This is general guidance, not legal advice.