A square-foot cost model is priced for one typical building: a set floor area, perimeter, number of stories and story height. Your building is never exactly that building. Four modifiers adjust the model to your facility, and getting them right is the difference between a replacement value that holds up and one that a reviewer can pick apart.
As a building’s total floor area increases, its cost per square foot generally decreases. Fixed costs such as mobilization, cranes, temporary facilities and project management are spread over more square feet, and larger projects benefit from bulk purchasing and repetitive labor. A building smaller than the model loses those economies, so its cost per square foot is adjusted upward.
The ratio of perimeter to floor area mainly drives the cost of the Shell (UNIFORMAT II B20 exterior enclosure), along with continuous perimeter foundations (A10). Two buildings with 10,000 SF of floor area will cost differently depending on shape:
A square has the shortest perimeter for its area, so it needs the least exterior wall, perimeter foundation and exterior finish. Rectangles, L-shapes and H-shapes of the same area need more envelope per square foot, which raises cost. Published models express this as an add or deduct per 100 linear feet of perimeter.
Enter the cost model’s base cost and typical size, then your building. The calculator computes perimeter from shape, then applies area, perimeter, story and story-height adjustments. The adjustment curves and cost shares are illustrative; replace them with the published factors from your cost source.
| Modifier | Basis | Factor | Effect on $/SF |
|---|
Illustrative method for planning. Use published cost data and a qualified estimator for real valuations. Not engineering or legal advice and not FEMA guidance. GovStar is independent and not affiliated with FEMA. Related: UNIFORMAT II Replacement Valuation Model · Funding & Valuation Center.