Independent FEMA Public Assistance resource. Not affiliated with FEMA.DeclarationsRecovery GuidesStart hereReform watchContact
GovStar guideFEMA PROCUREMENT UNDER GRANTS POLICY GUIDE · VERSION 2.2 (FY 2026)
2 C.F.R. §§ 200.317–200.327 • APPENDIX II TO PART 200

Procurement and Contracting

How to buy goods and hire contractors with FEMA money so the costs survive review: which rules apply to your disaster, how to compete each purchase, when you can sole-source, what every contract must contain, and how FEMA responds when procurement goes wrong. Built from FEMA’s Procurement Under Grants Policy Guide, Version 2.2, with its page numbers.
Read FEMA’s full Policy Guide (PDF) ↗
$15,000
Micro-purchase threshold

For purchases on or after Oct. 1, 2025 (was $10,000). Local governments and nonprofits may self-certify up to $50,000 (p. 58).

$350,000
Simplified acquisition threshold

Above it, formal methods, bonding and extra review apply. Was $250,000 before Oct. 1, 2025 (pp. 2, 63).

Oct. 1, 2024
Rules follow your declaration

This guide covers disasters declared and awards made on or after this date. Older disasters use older rules (pp. 4–6).

3+
Quotes FEMA encourages

FEMA encourages at least three price or rate quotations for competitive procurements (p. 63).

POLICY GUIDE · PP. 2–6 ↗WHICH RULES APPLY TO YOU
2 C.F.R. PART 200 (REV. OCT. 1, 2024)

1. Which Rules Apply to You

The procurement rules that govern your contract are fixed by the date of your disaster declaration (or, for non-disaster grants, the federal award date in your Notice of Award), not by the date you sign the contract. The dollar thresholds are the exception: they follow the date of the purchase.

Declaration or award dateRules and FEMA guidanceNotes
On or after Oct. 1, 2024Revised 2 C.F.R. Part 200; Procurement Under Grants Policy Guide (this guide)Also applies to every Hurricane Helene declaration, including those declared before Oct. 1, 2024; FEMA amended those agreements (p. 5).
Nov. 12, 2020 – Sep. 30, 2024FY21 PDAT Field ManualPre-2024 rules: “small purchases,” no U.S.-jobs scoring, geographic-preference ban still in force.
Dec. 26, 2014 – Nov. 11, 2020FY16 Field Manual Supplement and FY19 Field ManualEarlier versions remain the rule for awards and declarations in their date range (p. 5).
Before Dec. 26, 2014FY14 Field ManualPre-Uniform Guidance rules.

SOURCE: POLICY GUIDE PP. 4–6 (APPLICABILITY TABLE)

Thresholds follow the purchase date

  • Purchases on or after Oct. 1, 2025: micro-purchase $15,000; simplified acquisition $350,000.
  • Purchases Oct. 1, 2024 – Sep. 30, 2025: micro-purchase $10,000; simplified acquisition $250,000.
  • Your own lower limits govern: if your state, local or tribal threshold is lower, you must use it, because you have to comply at every level (pp. 59, 63).

POLICY GUIDE PP. 2, 58–63 • FAR 2.101 INFLATION ADJUSTMENT (OCT. 1, 2025)

What changed in the 2024 rules

  • Indian Tribes now follow their own procedures, like States.
  • “Board members” added to conflict-of-interest rules.
  • Contractor responsibility now includes correct worker classification under the Fair Labor Standards Act.
  • “Double dipping” defined and prohibited.
  • Geographic-preference ban removed; scoring that rewards U.S. jobs allowed.
  • “Small purchases” renamed “simplified acquisitions.”
  • Separate profit negotiation no longer required when there is no price competition.

POLICY GUIDE PP. 2–4 (LIST OF CHANGES)

Watch out: a contract signed in 2026 for a disaster declared in 2023 is judged under the FY21 Field Manual rules. Use the Rules Finder in Interactive Tools to confirm which set applies before you solicit.
2 C.F.R. §§ 200.317–200.318

2. Who Follows What

The rules split by type of entity. States and Indian Tribes follow their own written procurement policies. Local governments and nonprofits follow the full federal standard in 2 C.F.R. §§ 200.318–200.327, plus any stricter state or local rule. FEMA is never a party to your contracts; its relationship is with the award recipient (p. 11).

RequirementStates & TribesLocal govts & nonprofits
Which proceduresTheir own documented policies used for non-federal funds (§ 200.317). With none in place, they must follow §§ 200.318–200.327.Their own procedures, which must meet §§ 200.318–200.327. The most restrictive of local, state and federal rules controls.
Domestic preference and required clausesMust comply with § 200.322 and § 200.327Must comply
Written conflict-of-interest rules and written disclosure to FEMARequired by FEMA policy, including organizational conflicts (p. 15)Required (§ 200.318(c)), with board members now covered
Cost-plus-percentage-of-cost contractsNot barred by § 200.317, but FEMA may question cost reasonableness (pp. 14, 113)Prohibited (§ 200.324(c); p. 112)
Recovered materials (§ 200.323)States must comply; Tribes exemptLocal governments must comply; nonprofits exempt

SOURCE: POLICY GUIDE PP. 13–23, 105–106, 112–113

Contract types

  • Fixed price: the contractor carries the cost risk. Preferred for well-defined work (p. 12).
  • Cost-reimbursement: pays allowable costs; needs a ceiling and close monitoring (p. 12).
  • Time-and-materials: allowed for local governments and nonprofits only when no other type is suitable and the contract has a ceiling the contractor exceeds at its own risk (p. 41).
  • Cost plus a percentage of cost: banned for local governments and nonprofits; a ceiling price does not cure it (p. 112).

Joint purchases cross the line

When a State or Tribe buys jointly with a local government or nonprofit, the whole procurement must meet the federal standards for every participating entity type, not just § 200.317 (p. 138).

POLICY GUIDE · PP. 24–47 ↗GENERAL PROCUREMENT STANDARDS
2 C.F.R. § 200.318

3. Standards & Conflicts of Interest

Every local government and nonprofit procurement must meet these mandatory standards, whatever the method or dollar amount.

Mandatory standards

  • Oversight: keep oversight so contractors perform to the terms of the contract (p. 25).
  • Written standards of conduct covering employees, officers, agents and board members who select, award or administer contracts, with disciplinary actions for violations (p. 25).
  • Gifts: no gifts, gratuities, favors or anything of monetary value from contractors. Your standards may allow unsolicited items of nominal value or interests that are not substantial (pp. 25–26).
  • Conflicts of interest: no one may take part in selecting or administering a contract if they, family, a partner or a prospective employer has a financial or other interest in a competing firm. Organizational conflicts with parents, affiliates and subsidiaries must also be addressed (p. 26).
  • Need determination: avoid unnecessary or duplicative purchases; consider consolidating or breaking out purchases for economy, and leasing versus buying (p. 30).
  • Contractor responsibility: award only to responsible contractors. Consider integrity, public-policy compliance, past performance, financial and technical resources and proper worker classification under the Fair Labor Standards Act. Check SAM.gov for exclusions (p. 33).
  • Time-and-materials limits: only when no other contract type is suitable and with a ceiling price (p. 41).

POLICY GUIDE PP. 24–43

The procurement file FEMA expects

Records must detail the history of each procurement (p. 36):

  • Rationale for the procurement method
  • Selection of contract type
  • Contractor selection or rejection
  • Basis for the contract price
  • The signed contract and every signed modification

Retention: three years from submission of the final expenditure report, longer if litigation, claims or audit findings are open, and three years after final disposition for property and equipment (p. 36; 2 C.F.R. § 200.334).

Encouraged, not required: federal excess and surplus property, value engineering clauses on construction, and strategic sourcing or shared purchasing arrangements (pp. 43–44).
POLICY GUIDE · PP. 48–56 ↗FULL AND OPEN COMPETITION
2 C.F.R. § 200.319

4. Competition

All procurement transactions must be conducted in a way that provides full and open competition. FEMA treats these situations as restrictive of competition (pp. 48–54):

Seven practices that restrict competition

  • Placing unreasonable requirements on firms to qualify (p. 49)
  • Requiring unnecessary experience or excessive bonding (p. 49)
  • Noncompetitive pricing practices between firms or affiliated companies (p. 50)
  • Noncompetitive contracts to consultants on retainer (p. 51)
  • Organizational conflicts of interest (pp. 52–54)
  • Specifying only a brand name instead of “brand name or equal” with the salient characteristics described (p. 54)
  • Any arbitrary action in the procurement process (p. 54)

Double dipping is prohibited

A local government or nonprofit may not hire a contractor to write the scope of work or specifications and then let that same contractor bid or propose on the work (§ 200.319(b); p. 52).

Written procedures must

  • Describe requirements clearly and accurately, without unduly restricting competition (p. 55)
  • Identify all requirements and evaluation factors (p. 55)
  • Keep prequalified lists current with an adequate number of sources, using objective factors that evaluate price and cost (p. 55)
  • Optionally score bidders on commitments to specific numbers and types of U.S. jobs (§ 200.319(f); p. 56)
New since 2024: the federal ban on geographic (in-state or local) preferences is gone from the Federal Procurement Standards (p. 3). Check your own state and local law before using one.
POLICY GUIDE · PP. 57–85 ↗METHODS OF PROCUREMENT
2 C.F.R. § 200.320

5. Choosing a Method

Local governments and nonprofits choose the method by the expected total value of the purchase, using the federal threshold or their own lower threshold, whichever is lower. Splitting a purchase to get under a threshold is prohibited (pp. 59, 63).

MethodValueCompetitionKey rules
Micro-purchase
P. 58
Up to $15,000 (self-certify up to $50,000)No quotes required if the price is fair and reasonable; distribute purchases equitably among qualified suppliers.Document why the price is reasonable; award only to responsible contractors.
Simplified acquisition
P. 63
$15,000.01 – $350,000Price or rate quotes from an adequate number of qualified sources; FEMA encourages at least three.Fixed price or not-to-exceed; no splitting, and no low-balling the scope then adding a change order that pushes it over $350,000.
Sealed bids
P. 69
Over $350,000Publicly advertised; bids opened publicly at the stated time.Preferred for construction. Firm fixed price to the lowest responsive, responsible bidder; reject bids only for a sound, documented reason.
Proposals (RFP)
P. 77
Over $350,000Publicized; all evaluation factors and their relative importance stated; written evaluation method.Fixed price or cost-reimbursement. For architect and engineer services only, select on qualifications without price, then negotiate a fair price with the top-ranked firm (p. 134).
Noncompetitive
P. 86
Any amountOnly in the five situations in § 200.320(c).Written justification for each (except micro-purchases) and a cost analysis. See section 6.

Self-certifying a higher micro-purchase threshold

Local governments and nonprofits may self-certify up to $50,000 a year with a written justification and support for one of: low-risk auditee status, an annual internal risk assessment, or (for public institutions) a higher threshold under state law. Above $50,000 needs approval from the cognizant agency for indirect costs (p. 58).

Sealed bids: when they are required

  • Complete, adequate and realistic specifications or purchase descriptions are available
  • Two or more responsible bidders have been identified
  • The procurement lends itself to a fixed price contract
  • The bidder is selected primarily on price

POLICY GUIDE PP. 69–70

Watch out: awarding a $340,000 simplified acquisition and then adding an out-of-scope change order that takes it past $350,000 is the pattern FEMA describes as an improper way around formal competition (p. 63).
POLICY GUIDE · PP. 86–99 ↗NONCOMPETITIVE PROCUREMENT
2 C.F.R. § 200.320(c)

6. Sole Source & Emergencies

A local government or nonprofit may skip competition only in five situations. Even then, every other rule still applies: cost analysis, contract provisions, T&M limits and the ban on cost-plus-percentage-of-cost contracts (p. 93).

The five situations

  • Micro-purchase: the total does not exceed the micro-purchase threshold (p. 86).
  • Single source: the item or service is available from only one source (p. 86).
  • Public emergency or exigency will not permit the delay of a competitive solicitation (p. 87).
  • FEMA or pass-through approval: FEMA or the pass-through entity expressly authorizes it in response to your written request (p. 90).
  • Inadequate competition: after soliciting an adequate number of sources, competition is determined inadequate (p. 91).

The last four require a written justification for each procurement.

Emergency vs. exigency

Emergency: a threat to life, public health or safety, improved property or another dangerous situation requiring immediate action. Generally shorter-lived. Example: a hospital loses power and its backup generators fail.

Exigency: a need to avoid, prevent or alleviate serious harm or injury, financial or otherwise, where competitive procedures would prevent the urgent action required. Example: sole-sourcing debris removal so a downtown business district can reopen.

POLICY GUIDE P. 88

The authority ends when the circumstance ends. Noncompetitive contracts may cover only work tied to the emergency or exigency that existed when you awarded them. FEMA expects you to start competing the follow-on work immediately after a noncompetitive award, and failure to plan the transition is not a reason to keep sole-sourcing (pp. 88, 93). Waiving your own state or local procurement rules for a disaster does not waive the federal standards (p. 89).

What a sole-source justification should contain

  1. Which § 200.320(c) circumstance applies.
  2. A brief description of the product or service and the expected dollar amount.
  3. Why noncompetitive procurement is necessary; for an emergency or exigency, the specific conditions that make competition an unacceptable delay.
  4. How long the contract will be used for the defined scope, and what would happen to that scope without it.
  5. The transition plan to competitively procured contracts.
  6. The cost analysis and other compliance steps (contract provisions, responsibility, conflicts).

POLICY GUIDE PP. 93–94 (SUGGESTED ELEMENTS); OUT-OF-SCOPE CHANGES ARE TREATED AS NEW SOLE-SOURCE AWARDS (P. 93)

POLICY GUIDE · PP. 109–119 ↗CONTRACT COST, PRICE AND BONDING
2 C.F.R. §§ 200.324, 200.326

7. Cost, Price & Bonding

Price analysis and cost analysis

  • Independent estimate first: local governments and nonprofits must make their own cost estimate before receiving bids or proposals (pp. 109–110).
  • Above $350,000: a cost or price analysis is required for every procurement, including contract modifications (§ 200.324(a)).
  • Price analysis looks at the total price: comparing offers, prior prices, published prices, your estimate or market research (p. 109).
  • Cost analysis reviews each cost element and the proposed profit; needed where there is no price competition, such as sole-source awards (p. 110).
  • Workforce impact: you may consider effects on public-sector employees if the contract would displace them (p. 109).
  • Profit: negotiating profit as a separate element is no longer required, but its reasonableness still matters (p. 4).

Cost plus a percentage of cost: FEMA’s four-part test

Prohibited for local governments and nonprofits, including in subcontracts under cost-type prime contracts. A contract is a prohibited CPPC contract when (p. 112):

  1. Payment is a predetermined percentage rate;
  2. The rate applies to actual performance costs;
  3. The contractor’s entitlement is uncertain when the contract is signed; and
  4. The entitlement grows as performance costs grow.

A ceiling price does not make it acceptable. Watch for “T&M” contracts that add a percentage markup to materials or subcontracts.

Construction bonding over $350,000

Local governments and nonprofits must require these on construction or facility improvement contracts and subcontracts, including modifications, that exceed the simplified acquisition threshold, unless FEMA or the pass-through entity accepts their own bonding policy (pp. 109, 117–118):

BondAmountPurpose
Bid guarantee5% of the bid priceAssures the bidder will sign the contract and provide the required bonds (p. 117)
Performance bond100% of the contract priceSecures fulfillment of all contract obligations (p. 118)
Payment bond100% of the contract priceAssures payment of everyone supplying labor and materials (p. 118)

Requiring bonds that go beyond what the work needs can itself restrict competition (p. 49).

POLICY GUIDE · PP. 120–130 ↗REQUIRED CONTRACT PROVISIONS
2 C.F.R. § 200.327 • APPENDIX II

8. Contract Clauses

Every contract funded under a FEMA award must contain the applicable Appendix II provisions. Missing clauses are among the most common findings. The Clause Checklist in Interactive Tools tells you which ones a specific contract needs.

ProvisionApplies whenNotes
Remedies for breachOver $350,000Administrative, contractual or legal remedies and penalties (p. 121)
Termination for cause and convenienceOver $10,000How termination works and the basis for settlement (p. 121)
Davis-Bacon and Copeland Anti-KickbackConstruction over $2,000, listed programs onlyEMPG, HSGP, NSGP, THSGP, PSGP, TSGP, Intercity Passenger Rail, Safeguarding Tomorrow RLF and High Hazard Potential Dams. Not PA (p. 122)
Contract Work Hours and Safety StandardsOver $100,000 with laborers or mechanicsOvertime and safety standards (p. 122)
Rights to inventionsFunding agreements onlyDoes not apply to PA, HMGP, FMA, BRIC, FMAG and other listed programs (p. 123)
Clean Air Act and Water Pollution Control ActOver $150,000Compliance with federal air and water standards (p. 123)
Suspension and debarment$25,000 or moreCovered transactions; check SAM.gov exclusions (p. 124)
Byrd Anti-Lobbying certificationOver $100,000Each tier certifies to the tier above; subcontracts over $100,000 included (p. 125)
Procurement of recovered materialsStates and local governmentsEPA-designated items over $10,000 a year; not Tribes or nonprofits (p. 126)
Covered telecommunications banAll contractsNo covered equipment or services under 2 C.F.R. § 200.216 (p. 126)
Domestic preferencesAll contractsPreference for U.S. goods to the extent practicable (§ 200.322; p. 127)
Build America, Buy AmericaInfrastructure under covered programsNot most disaster programs: not PA, HMGP or IA (pp. 101–103, 127)

FEMA-recommended (not required): access to records, changes and modifications, DHS seal and logo, compliance with federal law, no federal obligation, program fraud and false statements, and copyright (pp. 127–129).

2 C.F.R. §§ 200.318–200.327

9. Disaster Contracting

Contract changes

A change must stay within the scope of the contract (the nature of the work, its cost and its period of performance) and the scope of the competition (whether the original solicitation told bidders this kind of change could happen). An out-of-scope, “cardinal” change is treated as a new sole-source award that needs its own justification (pp. 132–133, 93).

Construction delivery

  • A/E services: qualifications-based selection without price, then price negotiation (p. 134)
  • Design-bid-build: design first, then sealed bids (p. 134)
  • Design-build: one contract for design and construction, procured by proposals (p. 135)
  • Construction manager at risk: the manager’s subcontracts must be competed under the federal standards (p. 136)

Joint purchasing and piggybacking

Joint procurement (encouraged): two or more entities solicit and award together from the start, with every party in the scope (pp. 137–138).

Piggybacking (discouraged): using another jurisdiction’s contract is acceptable only if the original was procured under the standards that apply to you, it allows assignment, your work falls within its scope without cardinal changes, and the price is fair and reasonable. Otherwise FEMA views a local government’s or nonprofit’s piggyback contract as noncompetitive (pp. 139–140).

Prepare before the disaster

  • Prepositioned contracts for debris, generators and other recurring needs, competed before the incident and scoped for the size of event you may face (pp. 146–148)
  • Prequalified lists kept current and open to new sources (p. 144)
  • GSA Schedules and other cooperative programs, used under their rules (pp. 140–142)
  • Mutual aid agreements and purchasing agents, which still require compliant procurement (pp. 148–151)
2 C.F.R. §§ 200.325, 200.339, 200.208

10. Reviews & Remedies

When FEMA can ask to review documents first

Upon request, local governments and nonprofits must provide procurement documents (RFPs, IFBs, independent cost estimates) before award when (p. 115):

  • Their procedures do not comply with §§ 200.318–200.327
  • A procurement over $350,000 is to be awarded without competition, or only one bid is expected
  • A procurement over $350,000 specifies a brand name
  • A sealed-bid award over $350,000 is going to someone other than the apparent low bidder
  • A modification changes the scope or adds more than $350,000

A FEMA-reviewed or self-certified procurement system can exempt you from these reviews (p. 115). FEMA also reviews files after award (p. 116).

What FEMA may do about noncompliance

  • Temporarily withhold payments until the problem is corrected
  • Disallow all or part of the cost of the noncompliant activity
  • Wholly or partly suspend or terminate the award
  • Start suspension or debarment proceedings
  • Withhold further awards
  • Other legal remedies, such as asking you to change the official who manages the grant

Specific conditions can include reimbursement-only payment, holds on later project phases, extra reports and monitoring, required training or technical assistance, and added prior approvals (p. 153).

POLICY GUIDE PP. 152–154

“All or part” matters. The remedy is not automatically a full disallowance. If FEMA questions a procurement, document the reasonableness of the costs you paid and the circumstances you faced. For how FEMA has decided these disputes, search FEMA’s second-appeal decisions in GovStar’s Appeal Decisions Search.
INTERACTIVE TOOLSRULES FINDER • METHOD SELECTOR • CLAUSE CHECKLIST
BASED ON POLICY GUIDE V2.2

11. Interactive Tools

Quick checks for a specific purchase. They apply the rules summarized above; they are not legal advice, and your own state, local or tribal rules may be stricter.

Which rules and thresholds apply?

GovStar summarizes FEMA’s Procurement Under Grants Policy Guide, Version 2.2 (FY 2026), and 2 C.F.R. §§ 200.317–200.327. Page numbers refer to the Policy Guide (PDF); each section’s red source label opens it at that page. GovStar is independent and not affiliated with FEMA. This is general guidance, not legal advice; consult your servicing counsel on specific procurements.