FEMA Public Assistance declaration

DR-4222 Severe Storms, Tornadoes, Straight-Line Winds, And Flooding (Oklahoma)

Severe Storm(s)
|
Oklahoma
|
2015
64240912
$64.2M
net federal share obligated
1482
project worksheets
298
applicants
DR
declaration type (DR major disaster, EM emergency)

Where the dollars went, by FEMA work category

Net federal obligations for this declaration, with each category's share. Blue is emergency work, orange is permanent work.

A Debris Removal
1580627
B Emergency Protective Measures
3546596
C Roads and Bridges
38010573
D Water Control Facilities
1937062
E Buildings and Equipment
3142584
F Utilities
12154500
G Parks, Recreational and Other Facilities
1809449
Z Management and Administrative Costs
2059522
8
emergency work (categories A and B)
89
permanent work (categories C to G)
C Roads and Bridges
largest work category
Source: OpenFEMA, Public Assistance Grant Award Activities, obligations through 12 November 2026. Figures are net federal share obligated, with de-obligations subtracted: commitments, not final costs. A category can show a negative amount when de-obligations exceed obligations. Govstar is independent and not affiliated with FEMA, and FEMA states this data is not official federal financial reporting.