FEMA Public Assistance · Fixed-cost fundingStatus as of November 15, 2026

Small Projects and Fixed Costs

Most Public Assistance projects are small projects, and small projects are already funded the way reformers want all projects funded: on the estimate, not on final invoices. Get the estimate right and the money is yours to manage. Get it wrong and there is only one narrow way back.

In effect$1,130,900Small project maximum for disasters declared on or after October 1, 2026. Projects at or above it are large projects.
In effectPaid on the estimateFEMA does not adjust a small project to actual cost. The obligated estimate is treated as reasonable unless there is fraud, waste, abuse or noncompliance.
In effectOne way backIf your small projects together cost significantly more than obligated, a Net Small Project Overrun appeal is due within 60 days of the latest work completion date.

1How small projects work

Section 422 of the Stafford Act lets FEMA use simplified procedures for projects below a dollar threshold. FEMA raised that threshold to $1 million in 2023 and adjusts it every year for inflation. For major disasters and emergencies declared on or after October 1, 2026, the small project maximum is $1,130,900, a 3.4% increase. FEMA also sets a minimum project amount each year; work below it is not funded.

The threshold that applies is the one in effect on the declaration date, not the date you write the project. FEMA's Simplified Procedures policy (FP-104-23-001) covers small projects for emergency work, permanent work and debris removal under Sections 403, 406, 407 and 502. It does not cover management costs or donated resources.

The core rule

The estimate is the grant

Once FEMA obligates a small project, it does not true it up to actual cost. The estimate is treated as reasonable and eligible unless FEMA finds fraud, waste, abuse or noncompliance.

The trade-off

You carry the cost risk

If the work costs less, the savings stay with you. If it costs more, you absorb it unless your small projects as a group qualify for a net overrun appeal.

2Small projects vs. large projects

TopicSmall projectLarge project
ThresholdBelow $1,130,900 (disasters declared on or after October 1, 2026)$1,130,900 or more
Funding basisObligated estimate, or actual costs if the work is already completeEstimate at obligation, reconciled to documented actual costs
PaymentRecipient may pay the full federal share once the project is obligatedRecipient pays as work progresses and costs are documented
Cost overrunApplicant absorbs it, unless a Net Small Project Overrun appeal succeedsEligible, documented actual costs can be funded at reconciliation
Cost underrunApplicant keeps the savingsFunding is reduced to actual cost
CloseoutCompletion certification; no reconciliation to actual costFull reconciliation of actual costs
Estimate reviewCertified estimates are accepted subject to FEMA reviewAppendix L validation and the Cost Estimating Format for most permanent work

Project thresholds: small and large →

3Building an estimate that holds

Because the estimate becomes the funding, every gap in scope or price is permanent. The Simplified Procedures policy describes what FEMA accepts as cost support.

Labor

Force account labor

Estimated staff hours times average pay rates, with fringe benefits under your established policies.

Equipment

Equipment and materials

FEMA equipment rates for your own equipment. Purchase orders, rental agreements or the lowest of three quotes for the rest.

Contracts

Contract work

Bids received, or historical costs from recent, competitively procured contracts for similar work.

Construction

Professional estimates

Construction estimates must come from a licensed professional or certified estimator. Applicants may submit certified estimates for FEMA review.

Completed work

Actual costs

If the work is already finished when the project is written, it is funded on documented actual costs.

Check before you sign off

Common reasons small projects come up short

  • Scope missing items found later, such as hidden damage, code-required work or access costs.
  • Unit prices from before the disaster, without escalation for post-disaster market conditions.
  • Insurance reductions not anticipated in the estimate.
  • Mitigation left out, even though it can be added to a permanent work project if it is cost-effective.

Building cost estimates FEMA will accept → · Applicant and FEMA cost estimates →

4Savings and overruns

If it costs less

Keep the savings

FEMA does not reduce a small project to actual cost. FEMA's policy encourages applicants to use excess funds for activities that reduce future risk or improve future disaster operations.

If it costs more

Net Small Project Overrun appeal

If the combined actual cost of all your small projects in a disaster significantly exceeds the combined obligated amount, you may appeal. The appeal is due within 60 days of the latest work completion date among those projects and needs actual cost documentation for each.

It is a net test. Savings on some small projects offset overruns on others. One project going over does not, by itself, support an appeal. Track actual costs on every small project, even though FEMA will not reconcile them, so you have the numbers if you need them.

Small project closeout and net overruns →

5Closing out small projects

  1. 1

    Finish the work

    Complete the approved scope within the period of performance, or request an extension in time.

  2. 2

    Certify completion to the recipient

    Subrecipients certify that work is complete within 90 days of the latest work completion date.

  3. 3

    Recipient certifies to FEMA

    The recipient submits a Small Project Completion Certification within 180 days for subrecipient projects, or 90 days for its own projects. Extensions can be requested from the FEMA Regional Administrator.

  4. 4

    Keep the records

    Retain cost, procurement and completion records for the full record retention period. Audits can still find noncompliance after closeout.

Final reconciliation and closeout →

6Rules that still apply

Simplified procedures change how a small project is costed and closed. They do not change the rest of the program.

  • Eligibility. The applicant, facility, work and cost must still be eligible.
  • Procurement. Contracts must follow 2 CFR 200 procurement standards; noncompliant contracts can be disallowed.
  • Environmental and historic review. Required before work starts, except where an exemption applies.
  • Insurance. FEMA reduces funding by actual or anticipated insurance proceeds, and obtain-and-maintain requirements still apply.
  • Scope changes. Tell your recipient before changing the approved scope or doing alternate work.
  • Records and audits. Documentation and record retention rules apply in full.

7Practical tips

Tip 1

Estimate as if it is final

Because it is. Include escalation, access, code work and a realistic contingency.

Tip 2

Think about project grouping

How sites are combined decides whether a project falls under or over the threshold. Ask your recipient before splitting or combining work.

Tip 3

Record the completion date

The latest work completion date starts both the 60-day overrun appeal clock and the 90-day certification clock.

Tip 4

Track actuals anyway

You will need them for a net overrun appeal, for audits and to plan the use of any savings.

Tip 5

Check the threshold year

Use the threshold in effect on the declaration date. It changes every October 1.

Tip 6

Plan the savings

Decide early how you would use any underrun, such as for risk reduction or future disaster readiness.

8Where small projects fit in the move to fixed costs

Small projects are the oldest fixed-cost tool in Public Assistance. Section 428 extends the same idea to large permanent work through capped grants. The proposed Section 409 grants and Small Disaster Block Grants in H.R. 4669, and the Review Council's RAPID formula grants, would push it further. Skills built on small projects, especially estimating and cost tracking, carry over to every one of those models.

ModelStatusWho carries overruns
Small projectsIn effectApplicant, unless a net overrun appeal succeeds
Section 428 fixed-cost grantsIn effectApplicant
Section 409 grants (H.R. 4669)ProposedApplicant, after one allowed adjustment
Small Disaster Block Grant (H.R. 4669)ProposedState
RAPID (Review Council)ProposedState and its subrecipients

How FEMA Public Assistance funding is changing → · Section 428 fixed-cost projects →

9Sources

GovStar is an independent Public Assistance resource and is not affiliated with FEMA. This page is general guidance, not legal advice. Confirm thresholds, deadlines and requirements for your disaster with your recipient and FEMA.