Process guide · Stafford Act, 44 CFR Part 206, FEMA Policy 104-010
How Mission Assignments Work
A mission assignment is a FEMA work order that directs another federal agency to use its people, equipment and contracts in a disaster. This guide explains the two kinds, who signs, how an assignment moves from request to closeout, and what a state and its local applicants owe when they ask for Direct Federal Assistance.
FEMA separates support for the federal response itself from work done on behalf of a state, tribe or territory.
Federal Operations Support (FOS)
Direct Federal Assistance (DFA)
Purpose
Federal-to-federal support that lets FEMA coordinate the response: staging, logistics, liaisons, federal teams
Goods and services for eligible emergency work when a state, tribal or territorial (STT) government has exhausted its own capability
Who benefits
FEMA and other federal agencies
The STT government and its local applicants
Cost share
100% federal; no STT share
Federal share not less than 75%; STT share usually 25%, reduced when the President adjusts the cost share
Before a declaration?
Yes, when a declaration is reasonably likely and imminent ("surge"), funded from the Disaster Relief Fund
No; only after a Presidential declaration
STT signature
Not required
Required: the STT official signs to accept the scope of work and the cost share
Dollars since 2012
$2.02B across 9,101 assignments
$15.60B across 1,164 assignments
Fire Management Assistance Grant declarations do not support either kind of mission assignment under FEMA Policy 104-010-3. A separate Technical Assistance category was eliminated in 2013; that work now falls under DFA.
Who does what
Role
Who
Responsibility
Federal Approving Official (FAO)
FEMA official with delegated authority
Signs mission assignments and obligates funds; only FEMA staff with this authority can give a verbal tasking in an urgent, life-saving situation
FEMA Project Manager
FEMA program staff
Owns the assignment from creation to closeout: monitors progress, spending and the period of performance
Action Officer
The performing federal agency
Manages the agency's people and contracts, coordinates daily with FEMA and submits bills
STT Approving Official
State, tribal or territorial authorized representative
Signs every DFA assignment, accepting the scope of work and the obligation to pay the non-federal share
Lifecycle: request to closeout
1
Request
The state requests help on a Resource Request Form. FEMA decides whether a mission assignment is the right tool or whether a contract, an interagency agreement or a state-managed grant fits better.
2
Create
FEMA and the performing agency write the statement of work, a cost estimate and the period of performance. Pre-scripted mission assignments (templates for common needs such as temporary power or heavy-lift aviation) speed this up.
3
Approve and obligate
The Federal Approving Official signs and funds are obligated. For DFA, the state official also signs, which commits the state to the cost share.
4
Execute
The agency does the work. Task orders give site-level direction within the existing scope without adding money; amendments add or remove funds, change dates or change the cost share.
5
Inspect
For DFA, a final inspection report is completed when the work ends and is signed by the performing agency and the state.
6
Bill and close
The agency bills FEMA for actual costs, with dates, times and locations of work so the right state can be billed its share. FEMA reconciles, de-obligates unused funds and closes the assignment.
Time and money rules
Rule
What it says
Source
60-day DFA limit
Federal work under a DFA mission assignment is limited to 60 days after the declaration; extensions need FEMA regional approval for extenuating circumstances
44 CFR 206.208(d); FEMA Policy 104-010
Surge period
Pre-declaration surge FOS assignments have a recommended period of performance of 7 to 10 days
FEMA Policy 104-010-2
Two-year ceiling
Recovery assignments end by the second anniversary of the declaration; longer work moves to an interagency agreement. FOS assignments over one year are considered for conversion
FEMA Policy 104-010
Bill on actual cost
The state is billed its non-federal share of the final eligible cost, including the federal agency's overhead, not the original estimate
44 CFR 206.208
Billing and closeout
A bill marked final, or 180 days without billing activity and no valid reason, can start closeout; excess funds are de-obligated
FEMA Policy 104-010-2
Cost-share changes
A cost-share change is made by amendment; changing between FOS and DFA requires a new assignment
FEMA Policy 104-010
Order of authority: the Stafford Act governs (Sections 402, 403 and 502 authorize federal agencies to support state and local response at FEMA's direction). Next come the regulations in 44 CFR Part 206, which carry out the Act, then FEMA Policy 104-010 on mission assignments, then the Public Assistance Program and Policy Guide. When sources differ, the higher one controls.
Limits that protect the Disaster Relief Fund
No self-deployment
Agencies that deploy under their own authority or without FEMA approval are not reimbursed.
No paying for an agency's own job
FEMA may not mission-assign work that falls within the performing agency's own statutory authority.
No switching types
An assignment cannot be converted between FOS and DFA by amendment; a new assignment is required.
Written, even when urgent
Verbal taskings are allowed only when immediate action is imperative and must be confirmed in writing.
Emergency work only
DFA covers eligible emergency work and debris removal, not permanent repair.
Not for FMAG
Fire Management Assistance Grant declarations do not support mission assignments.
Emergency Support Functions and the Army Corps of Engineers
FEMA tasks agencies through the Emergency Support Functions of the National Response Framework. Since 2012, Public Works and Engineering (ESF-3) is 70% of DFA dollars.
Medical teams, patient movement, mass fatality support
ESF-10 Oil and Hazardous Materials
EPA, U.S. Coast Guard
Household hazardous waste, contaminated debris, spills in navigable waters
Temporary emergency power
Corps teams install and run generators at hospitals, water and wastewater plants, and public safety facilities.
Debris management
When local contractors are overwhelmed, the Corps manages clearance, sorting, reduction and disposal under a DFA assignment.
Temporary roofing
Operation Blue Roof installs fiber-reinforced sheeting so residents can stay in damaged homes until permanent repairs.
Corps of Engineers divisions received $13.54B of the $17.62B in mission assignments since 2012, including $8.11B to the South Atlantic Division alone. See the agency data
What states and local applicants owe for DFA
The 75/25 default
The federal share for emergency work, including DFA, is not less than 75%. The state, as recipient, owes the remaining share.
Relief can lower it
FEMA may recommend raising the federal share to 90% when federal obligations reach a per capita threshold ($189 per capita for 2026 disasters) and up to 100% for emergency work, including DFA, for a limited period early in the disaster.
The state decides the split
The recipient decides whether to pass part of the non-federal share to the local governments the work benefited. State law and the State Administrative Plan govern that split.
Billed on final cost
The bill follows final eligible cost plus agency overhead, often years after the event, so estimates at signing can differ from what is owed.
Location matters
The performing agency records where and when work was done so the share is billed to the right jurisdiction. Local governments should keep their own records of DFA work in their area.
Loans are available
44 CFR 206.45 allows FEMA to loan a state its non-federal share when it cannot pay; GovStar's state emergency management page covers state disaster funds.
Before you sign a DFA request: ask for the estimated cost and cost-share percentage in writing, agree internally who pays the non-federal share, and decide whether the same work could be done faster or cheaper with your own or pre-positioned contracts under Public Assistance Category A or B.
Checklist for state recipients
Request: document why state and local resources, including mutual aid and contracts, cannot meet the need.
Sign: review the scope, estimate, period of performance and cost share before signing a DFA assignment.
Track: log each DFA assignment, its amendments and the cost-share percentage in force.
Transition: plan the hand-back before the 60-day limit and request extensions early when needed.
Inspect: sign the final inspection report only when the work is complete.
Reconcile: compare the final bill with the work your jurisdictions saw, and budget for the non-federal share.
GovStar is independent and not affiliated with FEMA. This page summarizes federal regulations, FEMA policy and public proposals for general information; it is not legal advice. Confirm current requirements with FEMA and your state recipient.